Permit Number: T11CM01130
Parcel: 140290410

Review Status: Completed

Review Details: COMMERCIAL - TI

Permit Number - T11CM01130
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
04/20/2011 GERRY KOZIOL WWM REVIEW Passed
05/03/2011 RONALD BROWN BUILDING-COMMERCIAL REVIEW Denied 1. Minimum font size is 3/32" upper and/or lower case. Please revise all sheets with fonts smaller and resubmit.
2. Please provide structural cals for the HVAV equipment on the roof.
3. Please provide a toilet, a water dispenser and a mop sink in the warehouse.
4. Please show an existing building floor plan attached to the new building floor plan.
5. Please show how the existing building roof drains.
6. Please provide detail showing connection of new and existing buildings.
7. Please provide two sets of structural calculations.
8. Please provide special inspection certifications.
END OF REVIEW
05/04/2011 ROBERT SHERRY WATER REVIEW Approved
05/04/2011 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Denied 1. The design basis for the metal building (Butler letter of certification) indicates that the rainfall is only 2 inches per hour; revise the rainfall to 3 inches per hour. Reference: Table D-1, UPC 2006.
2. Provide the size of the rain gutter. Reference: Section 103.2.3 and Table 11-3, UPC 2006.
05/04/2011 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Denied 1. Revise the energy code analysis for the building envelope, coordinating the building components used in the analysis with those shown on the drawing. Continuous insulation is insulation that is continuous over framing members or furring strips and is free of significant thermal bridging; the insulation shown for the metal building is considered to be cavity insulation. Reference: Section 502, IECC 2006, as amended by the City of Tucson.
2. Provide structural calculations to verify that the existing roof is capable of supporting the additional dead load due to the installation of the roof top units. Reference: Section 302.1, IMC 2006.
3. Show the size, route, and termination of the drains for the evaporative coolers. Reference: Section 304.1, IMC 2006.
4. Show how adequate access is being provided for the equipment located on the roof. Reference: Section 306.5, IMC 2006.
05/11/2011 RAY MAJUTA ELECTRICAL-COMMERCIAL REVIEW Approved

Final Status

Task End Date Reviewer's Name Type of Review Description
05/17/2011 CPIERCE1 OUT TO CUSTOMER Completed
05/17/2011 SUE REEVES REJECT SHELF Completed