Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL - TI ALL
Permit Number - T11CM00984
Review Name: RESUBMITTAL - TI ALL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
05/02/2011 | DAVE MANN | FIRE | REVIEW | Approved | |
05/04/2011 | GERRY KOZIOL | WWM | REVIEW | Denied | NEEDS TO BUILD PUBLIC SEWER NEED 3RD FL PCRWRD CAPACITY REVIEW- CHAD AMATEAU- 740-6547 |
05/09/2011 | LEERAY HANLY | ELECTRICAL-COMMERCIAL | REVIEW | Approved | |
05/10/2011 | DAVID RIVERA | ZONING | REVIEW | Approved | |
05/11/2011 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. Show that the termination of the 6"-flue for the spa heater complies with the requirements of Section 503.5.4, IFGC 2006. 2. Provide specifications for the exhaust fan for the pool equipment room. [Original Comment: Provide a mechanical plan for this building, including any exhaust fans or other mechanical equipment that will be installed. Reference: Section 106.3.1, IMC 2006.] |
05/11/2011 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | Revise the roof plan (2/A9.10) to include either the dimensions or a reference to the appropriate details for the sizes of the scuppers, collector boxes, and downspouts for the ramada. [Original comment: Provide roof drainage calculations and plans. Provide overflow protection for the roof. Reference: Sections 1101.2, 1101.7, 1106.4, and 1107, IPC 2006.] |
05/11/2011 | RONALD BROWN | BUILDING-COMMERCIAL | REVIEW | Approv-Cond | The response to comment 5 indicates that the pool will be issued under a separate permit as a deferred submittal. If it is to have it's own separate permit it would not be considered a deferred submittal to this permit. |
05/11/2011 | BETH GRANT | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Completed | |
05/11/2011 | RONALD BROWN | ZONING HC | REVIEW | Passed | |
05/13/2011 | LAITH ALSHAMI | ENGINEERING | REVIEW | Approved |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
05/24/2011 | DELMA ROBEY | OUT TO CUSTOMER | Completed |