Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - TI
Permit Number - T11CM00408
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
02/10/2011 | DAVE MANN | FIRE | REVIEW | Approved | |
02/16/2011 | RONALD BROWN | BUILDING-COMMERCIAL | REVIEW | Denied | 1. Please provide large scale toilet plans showing all accessible requirements, dimensions and clear spaces. 2. Generic code copied details for accessibility are not acceptable. Please provide all accessibility requirements, dimensions, accessories and clear spaces on the actual toilet design elevations. 3. At detail 25/A8.2, the sink height is to be 2;-10" as per 2006 IBC, ICC (ANSI 117.1), Section 606.3. 4. Door nos. 102c and 102a are not compliant. Strike clearance is to be 18" as per section 404.2.3.1. 5. Please provide a hi/low water dispenser as required by sections 1109.5.1 and 602.4. 6. At door 110a, provide an 18" clearance as required by section 404.2.3.1. 7. Open up the store front glazing for the new door 100a. 8. The following sheets are not sealed and signed by the registrant: SP1, SP2 and S-1. END OF REVIEW |
02/16/2011 | BETH GRANT | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Passed | |
02/17/2011 | RAY MAJUTA | ELECTRICAL-COMMERCIAL | REVIEW | Denied | Project: T11CM00408 2440 Majestic Park Way #100 TI Manufacturing Electrical plans have been denied form the following: 1. Provide a description of the type of manufacturing process to occur. Provide information on types of materials to be handled, used or stored. Will any of these type of materials be hazardous, if non-hazardous to be used please indicate. 2.Sheet E-2 Key note 4 indicates a 75 KVA transformer is to be relocated to the mezz level, please indicate on the plan an elevation sheet showing the relocated transformer with required clearances around it. 3. How is the 10Kaic value for the new panel N arrived at ? Ray T Majuta, Elect Plan Ck, PDSD, City of Tucson, 2/22/11, Ray.Majuta@tucsonaz.gov |
02/23/2011 | GERRY KOZIOL | WWM | REVIEW | Approved | |
03/08/2011 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Clarify the location of the pressure reducing valve; detail4/p2 implies that it is located between the existing water meter and the existing reduced pressure-zone backflow preventer but the water riser diagram (2/p1) indicates that it is located inside the building, downstream of the first hose bibb. Reference: Sections 103.2.3 and 608.2, UPC 2006. 2. Clarify where detail 3/p2 (condensate drain to lavatory tailpiece connection) occurs; the keynotes on sheet p1 indicate an indirect termination over the service sinks. Reference: Section 103.2.3, UPC 2006. 3. Coordinate the water heater support design shown in detail 1/p2 with detail 29/a9.1. Reference: Section 103.2.3, UPC 2006. |
03/08/2011 | ROBERT SHERRY | WATER | REVIEW | Denied | Provide the size of the existing water meter and the existing reduced pressure-zone backflow preventer. Reference: Sections 610.1 and 610.2, UPC 2006. |
03/08/2011 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. Provide information regarding the work being conducted in the production rooms (H2 and F1 occupancies), the materials being used and the quantities of materials being used and stored. Reference: Sections 502.8 and 502.9, IMC 2006. 2. Revise the exhaust duct design for the heat recovery unit HR-1; exhaust ducts may not penetrate fire-rated building partitions nor contain fire dampers. Reference: Section 502.10.2, IMC 2006. |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
03/09/2011 | CPIERCE1 | OUT TO CUSTOMER | Completed |
03/09/2011 | SUE REEVES | REJECT SHELF | Completed |