Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL
Permit Number - T11CM00085
Review Name: RESUBMITTAL
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 03/15/2011 | RONALD BROWN | BUILDING-COMMERCIAL | REVIEW | Approved | |
| 03/15/2011 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. Comment still not resolved. With a flow rate of 1233 CFM, the 10" x 12" exhaust duct for KH-1 will have an air velocity of only 1480 feet per minute; lower than the required minimum velocity of 1500 feet per minute. Note: consider the size of the duct cleanout doors shown in detail 4/M2.1. [Show the location of the grease exhaust duct for the griddle hood, KH-1, and indicate the size of the duct. Reference: Sections 106.3.1 and 506.3.4, IMC 2006, as amended by the City of Tucson.] 2. Comment not resolved. With a flow rate of 800 CFM, the 8" x 10" exhaust duct for KH-2 will have an air velocity of only 1440 feet per minute; lower than the required minimum velocity of 1500 feet per minute. Note: consider the size of the duct cleanout doors shown in detail 4/M2.1. [Revise the size of the grease duct for the fryer hood, KH-2, to provide a minimum velocity of 1500 feet per minute (the mechanical floor plan shows a 14" x 12" duct and an exhaust flow rate of only 800 CFM). Reference: Section 506.3.4, IMC 2006, as amended by the City of Tucson.] |
| 03/15/2011 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | Comment still not resolved. Show how and where the correctly-sized cleanouts are to be provided for the 4" drain lines in the cooking and prep areas. Both of the drains, running south to north, change from 3" to 4" at some point but a cleanout is required at the point where the size changes. [Provide information to show that the cleanouts have been sized per Section 707.11, UPC 2006 (see the 4" drain lines in the cooking area and the prep area).] |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 03/17/2011 | CPIERCE1 | OUT TO CUSTOMER | Completed |
| 03/17/2011 | SUE REEVES | REJECT SHELF | Completed |