Plan Review Detail
Review Status: Completed
Review Details: PIA RESUBMITTAL
Plan Number - T10PI00002
Review Name: PIA RESUBMITTAL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
03/10/2010 | JOSE ORTIZ | DOT TRAFFIC | REVIEW | Approved | |
03/12/2010 | Blanca Espino | DOT ENGINEERING | REVIEW | Approv-Cond | PIA Plan 1. Please include a detail letter of explanation with the next submittal indicating where and how revisions were made. Single word responses are unacceptable. Include plans/redlines from previous plan submittal. 2. Sheet 2, Roadway Plan View: Stations 9, 10, & 14 have the same stationing with different offsets. Sta. 14 is the one in question. Correct. 3. Sheet 2, Detail E: Indicate the percent amount of compaction. See redlines. |
03/16/2010 | LANCE PETERSON | DOT STREET MAINTENANCE | REVIEW | Approved | No objection pertaining to Street Maintenance. |
03/18/2010 | RLEIGH1 | UTILITY CLEARANCES | COT STREETS DIVISION | Approved | |
03/18/2010 | RLEIGH1 | UTILITY CLEARANCES | COT WATER NEW DEVELOPMENT | Approved | |
03/18/2010 | RLEIGH1 | UTILITY CLEARANCES | PC WASTEWATER MGMT | Approved | |
03/18/2010 | RLEIGH1 | UTILITY CLEARANCES | QUEST COMMUNICATION | Approved | |
03/18/2010 | RLEIGH1 | UTILITY CLEARANCES | TUCSON ELECTRIC POWER CO | Approved | |
03/18/2010 | RLEIGH1 | UTILITY CLEARANCES | COX COMMUNICATION | Approved | |
03/18/2010 | RLEIGH1 | UTILITY CLEARANCES | SOUTHWEST GAS CORP | Approved | |
03/18/2010 | RLEIGH1 | UTILITY CLEARANCES | EL PASO NATURAL GAS | Approved | |
03/18/2010 | RLEIGH1 | UTILITY CLEARANCES | KINDER MORGAN ENERGY | Approved | |
04/06/2010 | GARY WITTWER | DOT LANDSCAPE | REVIEW | Approved | |
04/06/2010 | RICHARD LEIGH | PIA COORDINATOR | CUSTOMER CALLED; PLANS @ AMBASSADOR | Completed | Plans are tentatively approved. Please submit mylars for final review and signing. |
04/06/2010 | RICHARD LEIGH | PIA COORDINATOR | OUT TO CUSTOMER | Completed | Plans are tentatively approved. Please submit mylars for final review and signing. |