Permit Number: T10OT02465
Parcel: 21114007C

Review Status: Completed

Review Details: FLOODPLAIN

Permit Number - T10OT02465
Review Name: FLOODPLAIN
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
11/17/2010 ELIZABETH LEIBOLD ENGINEERING REVIEW Approved November 17, 2010
FLOODPLAIN USE PERMIT # T10OT02465
PROJECT ADDRESS: 13701 W Mile Wide Rd, Marana AZ 85653
APPLICANT'S NAME: SunPower of AZ
PROPERTY OWNER: Tucson Water (in Pima County)

This parcel lies in a FEMA Zone AO2 (map number 04019C 2175K). The applicant is authorized for improvements for a City of Tucson Water project, on the property described as:

Parcel 211-14-007C, ALL OF SEC 6 EXC N449' OF NE4 OF LOT 3 & LOT 1 & NE4 NW4 OF SEC 7 ALL IN T14S R11E EXC SAN JOAQUIN RD 734.01 AC, in a portion of Township 14 South, Range 11 East, Section 6, located approximately ½ mile west of North Avra Road and ¼ mile south of West Mile Wide Road,

for the purpose of improvements for Tucson Water solar photovoltaic array with equipment pad.

The applicant agrees to comply with City of Tucson Floodplain and Erosion Hazard, and if applicable, Watercourse Amenities, Safety and Habitat regulations, and are particularly bound by the conditions stated below. Violation of any of the conditions stated or referred to below, as determined by the City Engineer, shall be grounds for revocation of this permit. Responsibility for renewal of this permit, if necessary, is with the applicant. Issuance of this permit does not constitute a waiver of other requirements contained in the Tucson City Code, Land Use Code, or any other Federal, State, County, or local regulation. No use other than as permitted herein is allowed. Additional uses allowed under the City of Tucson Floodplain and Erosion Hazard Regulations require the issuance of an additional Floodplain Use Permit.

The following 14 conditions apply to permit T10OT02465:
1) Call for Pre-construction meeting, SWPP, fence/gate installation, fill, toedown, & rip rap for equipment pad, and elevation certification inspections, and final inspection. For a PDSD Engineering Inspection, call IVR (740-6970), or contact PDSD Engineering at 837-4991, or schedule inspections online at: http://www.ci.tucson.az.us/dsd/Online_Services/Online_Permits/online_permits.html
2) Fence openings will be inspected by PDSD Engineering.
3) This Floodplain Use Permit and plans shall be kept in a readily accessible location on site at all times.
4) No disturbance other than the area shown on the approved plans.
5) PDSD Engineering Inspections are required prior to final floodplain inspection.
6) Note that the location of the site is incorrectly shown on the cover sheet T-1.0. The project is located approximately a half mile west of North Avra Road and a quarter mile south of West Mile Wide Road.
7) All work shall conform to the approved plans for the Tucson Water T-O Tracker Photovoltaic Array 13701 W Mile Wide Rd project only. Installation Plan - T-O Tracker Photovoltaic Array City of Tucson Water Department plans sealed by Jason Mercer, P.E. (10-13-10) are a part of the floodplain use permit. See also Hydrology Hydraulics, Scour/Erosion Summary Report for T-O Tracker Solar System by TetraTech, Inc. sealed 08/03/09 by Michael E. Zeller, P.E., Geotechnical Evaluation by Ninyo & Moore sealed by Steven Nowaczyk, P.E., and SWPPP dated 09/15/2010.
8) Submit Elevation certification(s) by a Land Surveyor registered in Arizona for the equipment pad to be installed at the center of the fenced enclosed photovoltaic array. PDSD Engineering has the preliminary elevation certificate filled out for the RLS to use, as needed. Assure the lowest elevation of the constructed pad is provided in C2e) and E4. Notations should be added to clarify type of equipment and location. Also be aware that the minimum pad elevation must be no lower than 3.00 feet above highest adjacent grade, or the inspection and elevation certificate will be rejected. First elevation certificate must be submitted prior to pouring concrete slab to assure minimum height is achieved. Concrete slab may not be poured until PDSD Engineering accepts first elevation certificate.
9) Submit copy of field reports from Civil or Geotechnical Engineer inspections for compaction of trenches, pier excavation depths, fill for equipment pad, and toedown depth for equipment pad. See T10CM02914 for separate Special Inspection Certifications that are needed for this project.
10) Within 5 (five) days of issuance of this permit, and through completion of the project, notification must be posted and maintained in a conspicuous place on the job site stating "CONSTRUCTION PROCEEDING UNDER REQUIREMENTS OF CITY OF TUCSON FLOODPLAIN USE PERMIT # T10OT02465. FOR INFORMATION PLEASE CALL 791-5550."
11) Except as approved by the City Engineer prior to the start of construction, development under this permit shall not obstruct, retard or divert the existing flow of floodwaters from or to adjacent properties.
12) This permit becomes invalid and is subject to additional floodplain review, if any required development permit changes the configuration of the improvement, or, if there is any further disturbance within the floodplain other than that outlined in this application. This floodplain use permit may be subject to conditions or restrictions designed to reduce or mitigate the potential damage or hazard to life or property resulting from development within the regulatory floodplain, floodway or erosion hazard areas as determined by the project engineer and accepted by the City of Tucson and PCRFCD.
13) All conditions of Pima County Regional Flood Control District Floodplain Use Permit No.10-369 approved 8/5/10 shall apply.
14) See also associated grading permit: T10BU01609, structural "Foundation only" permit: T10CM03253, and electrical permit: T10CM02914.

This Floodplain Use Permit will be automatically revoked and becomes invalid for non-compliance to conditions set forth in this permit. Also, this permit will expire 2 years from its date of issue. Renewal of this permit will require a new application, review and approval of that application by the City of Tucson, Planning & Development Services Department, Engineering Division.

(EXPIRATION DATE) Month: 11 Day: 16 Year: 2012

APPLICANT: Rita Soto, SunPower Corp.
ADDRESS: 1414 Harbour Way South, Richmond CA 94804
PHONE: (510) 260-8463
OWNER: Tucson Water

Final Status

Task End Date Reviewer's Name Type of Review Description
11/17/2010 CPIERCE1 OUT TO CUSTOMER Completed