Permit Number: T10CM03492
Parcel: 10707003H

Review Status: Completed

Review Details: COMMERCIAL - TI

Permit Number - T10CM03492
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
01/04/2011 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Approved
01/05/2011 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Denied 1. Clarify the size of the water service to the new kitchen. The plumbing floor plan (1/P1.1) indicates a 1-1/4" water service but the plumbing site plan (2/P1.1) calls for a 1-1/2" water service. Reference: Section 103.2.3, UPC 2006.
2. Detail 4/P2.1 calls for the water heater having a set point of 180 degrees Fahrenheit. Show how scald protection is to be provided. Reference: Section 103.2.3, UPC 2006.
3. Include all fixtures and the water requirements of the HVAC equipment when calculating the total demand and determining pipe sizes. Reference: Section 610.1, UPC 2006.
4. Revise the submitted water pressure calculations using the minimum daily water pressure. Reference: Section A3.3, UPC 2006.
5. A demand flow of 98 GPM through a 2" water meter results in an excessive pressure drop and a velocity greater than the maximum 8 FPS allowed for either plastic or copper piping. Reference: Sections 610.2 and 610.12, UPC 2006.
6. Clarify the manufacturer and model of the hydromechanical grease interceptor to be installed; the plumbing plan calls for a Schier "Great Basin" unit but the Architectural plans call for a Dormont "WD-50" unit. Reference: Section 103.2.3, UPC 2006.
7. The Schier "Great Basin" model GB-250 is listed as a gravity grease interceptor, ASME Standard A112.14.3. A gravity grease interceptor shall be sized per Table 10-3, UPC 2006 or the maximum drainage fixture units allowed for the size of the inlet pipe. Reference: Section 1014.3.6.1, UPC 2006.
01/05/2011 ROBERT SHERRY WATER REVIEW Approved
01/12/2011 RAY MAJUTA ELECTRICAL-COMMERCIAL REVIEW Denied Project: T10CM03492
2727 N Fairview

The Electrical Plans have been denied for the following:

1. Sheet E-2, circuit KE-1 on power plan should be KE-2,
Circuits KE-28,30 should be KM-28,30.
2. KE-8 listed as spare in Panel ,used in plan.
3. Sheet E-2, keynote #10 list a 100 amp disconnect fused at 90 amps, Sheet E-4 list a 200 amp disconnect fused at 150 amps feeding the new 112.5 kva transformer. The conductors sizes are also different for each.
4. Sheet E-2 shows a disconnect for Keynote #17, there appears to be a piece of electrical equipment in this area, will the required clearance be met ?
5. The total va's for Panel KE are incorrect, when adding the total of each phase and using 65% deration for kitchen equipment, the total is different.

Ray T Majaauta,
Elect Pln Ck,
PDSD,City of Tucson,
1/12/11,
Ray.Majuta@tucsonaz.gov

Final Status

Task End Date Reviewer's Name Type of Review Description
01/18/2011 CPIERCE1 OUT TO CUSTOMER Completed
01/18/2011 SUE REEVES REJECT SHELF Completed