Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL
Permit Number - T10CM03487
Review Name: RESUBMITTAL
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 05/17/2011 | RONALD BROWN | BUILDING-COMMERCIAL | REVIEW | Denied | Resubmittal Comments: 1. GENERAL: PROVIDE FULL SIZED DRAWINGS SIGNED AND SEALED BY THE ENGINEER OF RECORD DEPICTING THE MONOPOLE FOUNDATION AND REINFORCING, INCLUDING PIER DIAMETER, DEPTH, VERTICAL REINFORCING, TIES, AND THE NEW EQUIPMENT SLAB. 1a. No structural details are shown on the drawings as directed. 2. GENERAL: PROVIDE FULL SIZED DRAWINGS SIGNED AND SEALED BY THE ENGINEER OF RECORD DEPICTING THE MONOPOLE, CRITICAL ELEVATIONS OF ANTENNA ARRAYS AND POLE SPLICES, CONNECTION OF THE ANTENNA BRACKETS TO THE POLE, CONNECTION AT THE POLE SPLICES, MONOPOLE BASE PLATE AND ANCHOR BOLT DETAILS. 2a. No structural details are shown on the drawings as directed. 3. GENERAL: PROVIDE A DETAILED COST ANALYSIS FOR ALL MATERIALS AND LABOR OF THIS PROJECT, INCLUDING THE MONOPOLE, ANTENNA ARRAYS AND BRACKETS, MONOPOLE FOUNDATION, NEW EQUIPMENT CONCRETE SLAB, NEW 8' TALL MASONRY WALL AND FOOTING, NEW ICE BRIDGE, NEW EQUIPMENT CABINETS, NEW PREFABRICATED EQUIPMENT SHELTER, AND NEW SWING GATES. 3a. No cost analysis provided 4. ok 5. GENERAL: PROVIDE WRITTEN RESPONSES TO ALL REVIEW COMMENTS. 5a. Written responses wre not complete. end of review |
| 05/25/2011 | JOE LINVILLE | ZONING | REVIEW | Denied | J. Linville for Steve Shields 1. The Cell Tower plan has been reviewed by Zoning Review Section but cannot approve the plan until all zoning comments or concerns have been addressed. 2. Per LAND USE COMPATABILITY comment 13 a ten (10) foot wide landscape buffer is required around the perimeter of the required site wall. Show the ten (10) foot wide landscape buffer on the site plan. Zoning acknowledges the letter dated April 26, 2010 from Michael W. Wyndken that allows for the existing natural vegetation to serve as the buffer. This letter does not eleminate the requirement for the ten (10) foot buffer around the perimeter wall. This buffer must be entirely on site. Note: The property south and east of the site is planned to be developed as Part of the Julian Wash Trail and Trailhead and retention of existing natural vegetation is not part of the approved drawings. 3) Photos of the site do not indicate any extensive vegetation in the proposed landscape buffers. The conditions for the case require groundcover plantings and canopy trees. revise the plans to document any existing plants that meet the conditions and add vegetation as necessary to achive a natural landscape border. 4. Zoning will re-review the Cell Tower plan on the next submittal to insure compliance. Additional comments may be forthcoming. If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956 C:\planning\celltower\t10cm03487.doc |
| 05/26/2011 | ELIZABETH LEIBOLD | ENGINEERING | REVIEW | Denied | SUBJECT: UofA Tech Park Cell Tower Review re-submittal LOCATION: 7501 S KOLB RD, T15S R15E Secs20, 21, 27, & 28, Ward 4 REVIEWER: Elizabeth Leibold, PE ACTIVITIES: T10CM03487 FLOODPLAIN: Balanced Basin Management Plan, FIRM 2855K SUMMARY: The subject property and proposed cell tower improvements are located within a Zone X-shaded 500-yr floodplain as shown on the Flood Insurance Rate Map (FIRM), Community- Panel No. 04019C-2855K, effective date February 8, 1999. Engineering Division of the City of Tucson Planning & Development Services Department has received and reviewed the re-submittal package. Engineering does not recommend approval of the plans until the remaining comments are addressed. COMMENTS: 1) SE-09-17 (Ord.10761): It was unclear whether partial compliance to the special exception conditions have been met from the response letter. Provide copy of special exception conditions, and show compliance of special exception conditions. In response letter and on plans with notes or on planview, clearly explain how project is in compliance for items 8, 13, 14, & 16. 2) DS Sec.10-02.2.3.1.5.G: Provide copy of lease agreement or license agreement for parcel owned by Az Board of Regents. Submit 2 copies of the supporting documentation, and response letter. I can be reached at 837-4934 if you have questions. Elizabeth Leibold, PE, CPM, CFM Civil Engineer Engineering Division Planning & Development Services Department |
| 06/03/2011 | BRIAN HEFFERNAN | COMMUNICATIONS | REVIEW | Denied | NEED COMMUNICATIONS INFORMATION SHEET. IF YOU NEED A COPY OF THIS FORM PLEASE CALL SUE REEVES @ 520-837-4923. |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 06/27/2011 | CPIERCE1 | OUT TO CUSTOMER | Completed |
| 06/27/2011 | SUE REEVES | REJECT SHELF | Completed |