| 12/03/2010 | ANY | BUILDING-COMMERCIAL | REVIEW | Active | |
| 12/03/2010 | ANY | WWM | REVIEW | Active | |
| 12/03/2010 | ANY | ELECTRICAL-COMMERCIAL | REVIEW | Active | |
| 12/03/2010 | BETH GRANT | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Active | |
| 12/03/2010 | Any | ZONING HC | REVIEW | Active | |
| 12/03/2010 | SREEVES1 | ADA | REVIEW | Passed | |
| 12/06/2010 | DAVE MANN | FIRE | REVIEW | Denied | Fire Comments: Sheet C1 1. The life safety information states the project has alarms, panic hardware, and smoke detection. None of the are shown on the plan. |
| 12/10/2010 | ROBERT SHERRY | WATER | REVIEW | Denied | Revise the site drawing to show the location and size of both the water meter and the reduced pressure backflow preventer assembly serving the office building. Reference: Section 103.2.3, UPC 2006 and Chapter 27, Article V, Section 27-76 (a), Tucson Code. http://www.tucsonaz.gov/water/docs/backflow-ord.pdf |
| 12/10/2010 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Clarify the plumbing code that was used to design the tenant improvement for this office. The Building Code Summary on sheet C1 calls out the 2006 UPC but the Code Analysis Data sheet submitted with the drawings calls out the 2006 IPC. This review was made using the 2006 UPC. 2. Revise the site drawing to include the following information: a. the location and size of the water meter b. the location of the main water lines and fire hydrants c. the location of the gas meter (if one exists or is planned) d. the location and size of the public sanitary sewer e. the location of the building connection to the public sewer f. the location, invert, and rim elevation of the next upstream and the next downstream manholes g. the first floor elevation for the building Reference: City of Tucson Development Standard No. 2-05.0, Section 2.3 D and Section 103.2.3, UPC 2006. 3. Provide the minimum plumbing facilities required by Table 2902.1 and Section 2902.2, IBC 2006, for business occupancy. 4. The specified drinking fountain does not meet the accessibility requirements as shown in Section 1109.5, IBC 2006. 5. Provide a design for the mounting shelf for the water heater WH-1. Reference: Sections 310.0 and 314.5, UPC 2006. 6. Clarify the termination of the T&P relief piping for WH-1. Provide information to show that the termination of a T&P relief from a water heater over a hub drain as shown in detail 8/P1 will not cause splashing or flooding. (Termination of a T&P relief from a water heater over an elevated service sink is not approved location.) Reference: Sections 608.5 and 804.1, UPC 2006. 7. Provide water pressure and water pipe sizing calculations. Reference: Section 610.1, UPC 2006 8. The wet vent noted in detail 8/P1 will require a minimum size of 2-1/2" because the minimum waste pipe for a sink is 2". Reference: Footnote 2, Table 7-3 and Section 908.2 UPC 2006. 9. Provide upper terminal cleanouts on horizontal drainage pipes exceeding 5 feet in length (horizontal drain lines serving sinks require cleanouts regardless of length). Reference: Section 707.4, UPC 2006. |
| 12/13/2010 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. Provide the installed weight of the fan coil units. Reference: Section 106.3.1, IMC 2006. 2. Show how the fan coils are being connected to the building structure and provide calculations to show that the building structure is not being adversely affected. Reference: Section 302.1, IMC 2006. 3. Revise the size of the condensate drains in accordance with Section 307.2.1, IMC 2006, as amended by the City of Tucson. 4. Provide calculations demonstrating adequate ventilation. Reference: Section 401.2, IMC 2006. 5. Revise the sequence of operation for the restroom exhaust fan so that all of the air supplied to the restrooms will be exhausted. Reference: Section 403.2.1 (4), IMC 2006. 6. Revise the mechanical design as required to avoid using the corridor as a return air duct. Reference: Section 601.2, IMC 2006. |
| 12/14/2010 | STEVE SHIELDS | ZONING | REVIEW | Denied | DSD TRANSMITTAL FROM: Steve Shields Lead Planner PROJECT: 3655 N. Romero Road T10CM03231 & T10CM03232 Building Plan (1st Review) TRANSMITTAL DATE: December 14, 2010 1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan until all zoning comments or concerns have been addressed. 2. Submit a site plan that meets the requirements of D.S. 2-02.0. Based on the provided building plan the site review is for full code compliance due to a building expansion of greater than 25%. 3. Zoning can not approve the building plan until the site plan has been approved. 4. Zoning will re-review the building plan on the next submittal to insure compliance with the approved and stamped site plan. Additional comments may be forthcoming. If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956 C:\planning\grading\t10cm03231.doc RESUBMITTAL OF THE FOLLOWING IS REQUIRED: |
| 12/14/2010 | JASON GREEN | ENGINEERING | REVIEW | Denied | DATE: December 14, 2010 SUBJECT: 3655 N Romero Road Site Plan- Engineering Review TO: Eric Miller LOCATION: T13S R13E Sec27 Ward 3 REVIEWERS: Jason Green, CFM ACTIVITY: T10CM03231 and T10CM03232 SUMMARY: Engineering Division of Planning and Development Services Department has received and reviewed the proposed building plan applications (T10CM03231 and T10CM03232) for the above referenced property. Engineering Division does not recommend approval of the building plans at this time. The following items need to be addressed: DRAINAGE REPORT: 1) DS Sec.10-01 and 10-02 and Chapter 26 Tucson Code: Provide a Drainage Report showing conformance with the Critical Basin requirements for this site along with all Floodplain related issues. The subject property falls within a Critical Basin watershed and within a FEMA Special Flood Hazard Area Zone AO1 and Shaded Zone X 100-year floodplain per the Flood Insurance Rate Maps 04019C1619K. Provide a report that discuss and details all aspects of the Development Standards and Floodplain Ordinance. 2) Verify if the existing structures are in conformance with Chapter 26 of the Tucson Code. Due to the location of the structures within the FEMA AO1 floodplain the minimum finished floor elevation (FFE) for both structures must be 2-feet above the highest adjacent natural grade. Provide 2 Elevation Certificates (one for each structure) verifying FFE requirements. If the structures are not elevated to the required 2-foot elevation then the project falls under a Substantial Improvement review per Section 26-4.1 "Non-conforming Development." SITE PLAN COMMENTS: 3) Due to the full code expansion requirement per the Zoning Section the site plan will be reviewed for conformance with Tucson Code Chapter 26 "Floodplain and Erosion Hazard Management" and Development Standards Sec.2-02, 3-01, 3-05, 6-01, 10-01, 10-02 and 11-01. Make sure that all dimensions, details, sections, keynotes, proposed improvements and all other aspects of this project meet the minimum requirements within the referenced sections and are reflected on the site plan sheets. 4) Provide a General Note to state that this property is subject to City of Tucson Floodplain and Erosion Hazard Management Chapter 26 of the Tucson Code due to the FEMA Special Flood Hazard Area per the Flood Insurance Rate Maps 04019C1619K. 5) Provide a General Note to state that a Floodplain Use Permit is required for both structures and for any other work proposed within the regulatory 100-year floodplain. The Floodplain Use Permits are required with the site plan application. 6) Provide a General Note to state the floodplain determination per FEMA FIRM Panel #1619K. Per the referenced panel the property falls within a FEMA Special Flood Hazard Area Zone AO1 and Shaded Zone X 100-year floodplain. 7) Clearly delineate on the site plan the 100-year floodplain limit per the referenced panel. 8) Be advised that further comments will be forth coming on submittal of the site plan and Floodplain Use Permits. GENERAL COMMENTS: Please provide a site plan, 2 Floodplain Use Permits, 2 Elevation Certificates (these may be produced and picked up at the Engineering Counter at Planning & Development Services for your surveyor) and Drainage Report that addresses the comments provided above. Include a comprehensive response letter addressing in detail responses to all of the above comments. Further comments may be generated upon submittal of the site plan and Floodplain Use Permit review. For questions or to schedule an appointment I can be reached at 837-4929. Jason Green, CFM Senior Engineer Associate Engineering Division COT Planning & Development Services |