Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL
Permit Number - T10CM02160
Review Name: RESUBMITTAL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
10/13/2011 | MICHAEL ST. PAUL | ZONING | REVIEW | Denied | Only unit can be allowed in the RX-1 zone. Hence, only one kitchen. |
10/14/2011 | KEN VAN KARSEN | BUILDING-RESIDENTIAL | REVIEW | Denied | PLAN REVIEW COMMENTS T10CM02160 R 10/14/11 Plan review for the above referenced structure has been completed. This letter reflects comments to be addressed. In order to facilitate a shorter back check time, we request that you please provide revised plans and calculations, highlighting any changes, along with a written response to each of the notated items indicating action taken. SCOPE OF REVIEW: The scope of this plan review covers architectural, plumbing, mechanical, energy conservation and electrical. All code references are to the 2006 International Residential Code, 2006 International Energy Conservation Code, and Arizona State amendments to the 2006 Uniform Plumbing Code. All features were checked only to the extent allowed by the submittals provided. All portions of this project are assumed to meet or will meet other departmental requirements, conditions and concerns before permit approval. GENERAL REQUIREMENTS: Show corrections and revisions on original tracings or a finished reproducible set. Return two sets along with a set of the first submission for reference. Pen or pencil corrections on final prints will not be acceptable. To avoid delays, ensure that all corrections have been made, are complete, and have been coordinated on all applicable detail and notate sheets. (Do not cloud the changes made for comment revisions). Incorporate changes on originals and provide two copied sets for review. All engineers and architects involved in the design of the structure are to seal the related sheets of plans, details and calculations in accordance with the rules of the State Board of Technical Registration. PROVIDE TWO SETS OF REVISED PLANS FOR PROCESSING ELECTRICAL PLANS: 1. Provide legible notation (minimum 3/32" lettering) on the panel schedules. 2. Remove the 240V Range circuit #15, 17 from panel 'B', Zoning RX1. 3. Show Bathroom receptacles on a separate 20 AMP circuit, E3603.4. 4. Show sub-panel 'A' & 'B' feeder over-current protection (wire size) on the 400A panel schedule, E3605.5. See Table E3605.1 for sizing feeder conductors. 5. Clarify the 3/0 and 4/0 feeder sizes shown on the Riser Diagram to the sub panels. The lugs on a 100A or 150A panel may not accept the oversized 3/0 or 4/0 conductor. If you have any questions please contact: Ken Van Karsen (520) 837-4912 City of Tucson Residential Plan Review |