Permit Number: T10CM01737
Parcel: 13711425F

Review Status: Completed

Review Details: POST 3RD PARTY REVIEW

Permit Number - T10CM01737
Review Name: POST 3RD PARTY REVIEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
07/28/2010 LAITH ALSHAMI ENGINEERING REVIEW Denied Laith Alshami, Engineering and Floodplain Review, 07/28/2010,

The submittal can not be approved until the Development Plan and Drainage Report are approved.
07/30/2010 GERRY KOZIOL WWM REVIEW Denied NEED APPROVED DP. SITE PLAN TO MATCH
07/30/2010 ROBERT SHERRY WATER REVIEW Denied Tucson Water limits a 1" meter to a maximum demand of 25 GPM. Provide a letter from Tucson Water confirming that the use of a 1" water meter will be allowed for this project. Reference: Sections 610.2 and 610.12, UPC 2006
08/04/2010 TERRY STEVENS ZONING REVIEW Denied 08/04/2010

Development Services Department
Zoning Review Section

Terry Stevens
Lead Planner

Comments:

1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed.

2. Zoning could not verify that the building plan was in compliance with the approved development plan. Please submit two copies of the approved and stamped development, landscape, and NPPO plans with the next building plan submittal.

3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved site/development plan. Additional comments may be forthcoming.