Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Number: T10CM01560
Parcel: 99999999A

Address:
1375 W AJO WY

Review Status: Completed

Review Details: COMMERCIAL NEW

Permit Number - T10CM01560
Review Name: COMMERCIAL NEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
06/09/2010 SREEVES1 ADA REVIEW Passed
06/10/2010 DAVE MANN FIRE REVIEW Denied Fire Comments:

The site plans Sheet 11 indicate the building has fire sprinklers. the fire hydrant is just over 300 feet from the most remote point on the building.

The building plans do not show a sprinkler system. Please clarify. A small change in the hydrant location may be required.
06/16/2010 JASON GREEN ENGINEERING REVIEW Denied Provide a copy of the stamped aprroved development plan S09-081 for building plan and canopy stamp approval. The plans may be brought through as a counter walk through once the development plan package has been finalized through CDRC.
06/17/2010 GERRY KOZIOL WWM REVIEW Denied need PDEQ construction authorization for new public sewer
need approval to abandoned portion of 8" sewer G-335 by Kurt Stemm PCRWRD 3rd floor
need construction authorization from Ray Montoya's group 1st floor RWRD
06/17/2010 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Denied 1. SHEET S2.1; SECTIONS M1A, M12 AND M16: THE SECTIONS DO NOT INDICATE FINISH GRADE. PROVIDE TO ENSURE THE GEOTECHNICAL REPORT REQUIREMENTS ARE MET (MINIMUM FOUNDATION DEPTH OF 1'-6" BELOW FINISH GRADE).
2. GENERAL: PROVIDE WRITTEN RESPONSE TO THE REVIEW COMMENT.
06/18/2010 ERIC NEWCOMB ZONING HC REVIEW Approved
06/18/2010 BETH GRANT COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Approved
06/18/2010 RAY MAJUTA ELECTRICAL-COMMERCIAL REVIEW Approved
06/21/2010 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Denied 1. The equipment schedule on sheet P1.1 calls for one dishwasher (#43) but it doesn't show up on sheet P2.2.
2. Keynote #4 on sheet P2.1 is listed as "not used" but it appears next to the floor sink for the coffee bar; is the note on the plan an artifact?
3. Clarify the configuration of the hydromechanical grease interceptor noted as "U" on sheet P1.1 and further described in keynote 11 on sheet P2.1 with regard to the flow control device. Is the flow control device "an accessible, vented flow control fitting" or an "integral flow control fitting"? No vent is shown on the plumbing plan. Also, what is the "Hotzi oven" referenced in note 11 on P2.1?
4. Clarify the hot water recirculation system described in plan note #2/P2.2 (i.e. provide a detail). Coordinate the descriptions of the water heater operation noted in plan note #2/P2.2 with the water heater description "J" in the plumbing fixture schedule, P1.1.
5. Show how the temperature of the hot water supply to the public lavatories is controlled. Reference: Section 413.1, UPC 2006 and Section 504.3, IECC 2006.
6. Provide a vacuum relief for the water heater (located above fixture outlets). Reference: Section 608.7, UPC 2006.
06/21/2010 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Approved
06/21/2010 STEVE SHIELDS ZONING REVIEW Denied DSD TRANSMITTAL

FROM: Steve Shields
Lead Planner

PROJECT: Quick Trip
T10CM01560 & T10CM01561
Building Plan (1st Review)

TRANSMITTAL DATE: June 21, 2010

1. The building plan has been reviewed by Zoning Review Section and matches what is shown on the approved development package. Once all other PDSD agencies have approved Zoning will approve the building and fuel canopy plans.

2. Zoning is available for an over-the-counter review once all other PDSD agencies have approved the plans. Please call or email to schedule an appointment for the review.

If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956

C:\planning\grading\t10cm01560.doc

RESUBMITTAL OF THE FOLLOWING IS REQUIRED:
06/21/2010 ROBERT SHERRY WATER REVIEW Approved

Final Status

Task End Date Reviewer's Name Type of Review Description
07/27/2010 GERARDO BONILLA OUT TO CUSTOMER Completed
07/27/2010 SUE REEVES REJECT SHELF Completed