| 05/14/2010 | DAVE MANN | FIRE | REVIEW | Approved | |
| 05/18/2010 | JASON GREEN | ENGINEERING | REVIEW | Approved | |
| 05/18/2010 | STEVE SHIELDS | ZONING | REVIEW | Denied | PDSD TRANSMITTAL FROM: Steve Shields Lead Planner PROJECT: Mr Heads T10CM01309 Site Plan (1st Review) TRANSMITTAL DATE: May 18, 2010 COMMENTS: Please resubmit revised drawings and a response letter, which states how all Zoning Review Section comments regarding the Land Use Code and Development Standards were addressed. 1. This site plan was reviewed for compliance with the City of Tucson Development Standards (D.S.) and Land Use Code (LUC) for full code compliance. 2. As this project encompasses two (2) separate parcels under different ownership a recorded Covenant Regarding Development and Use of Real Property will be required. Provide a copy of the recorded document with your next submittal. 3. D.S. 2-02.2.1.A.12 There is an "EXIST. DOOR" shown near the southwest corner of this project that opens up into the adjacent parcel vehicle parking area. Clearly indicate on the plan that this door does not encroach into the vehicle parking space and provide a cross access agreement that allows pedestrian access to and across the adjacent parcel to the south. 4. D.S. 2-02.2.2.A.3 Per Development Designator "33" and LUC Section 3.2.3.2.B the allowed Floor Area Ratio (FAR) is 1.50. Provide a FAR calculation that includes the allowed FAR and proposed FAR, see LUC Section 3.2.11. 5. Depending on how the above comments are addressed addition comments may be forth coming. If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956. C:\planning\site\t10cm01309 RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised site plan and additional requested documents. |
| 05/19/2010 | ANDREW CONNOR | NPPO | REVIEW | Passed | |
| 05/20/2010 | ANDREW CONNOR | LANDSCAPE | REVIEW | Passed | |
| 05/26/2010 | RONALD BROWN | ZONING HC | REVIEW | Denied | 1. Ditto ZONING Comment number 3. |
| 06/07/2010 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | Revise the site drawing to include the following information: a. the location and size of the water meter b. the location of the main water lines and fire hydrants c. the location of the gas meter (if one exists or is planned) d. the location and size of the public sanitary sewer e. the location of the building connection to the public sewer f. the location, invert, and rim elevation of all manholes and cleanouts g. the first floor elevation for the building Reference: City of Tucson Development Standard No. 2-01.1.0 2 3.8 D and Section 103.2.3, UPC 2006. |