Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL - TI ALL
Permit Number - T10CM00253
Review Name: RESUBMITTAL - TI ALL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
03/16/2010 | DAVE MANN | FIRE | REVIEW | Denied | Fire Comments: The following fire sprinkler design criteria must be on the sealed plans. 1. The hazard classification of the building, including any special hazards. The hazard class may have changed in this area. Please check the hazard class. How are tires stored per NFPA 13 Chapt 12. 2. The density required of the water supply. |
03/17/2010 | STEVE SHIELDS | ZONING | REVIEW | Denied | DSD TRANSMITTAL FROM: Steve Shields Lead Planner PROJECT: Sun Tran Expansion T10CM00251, T10CM00252, T10CM00253 Building Plan (2nd Review) TRANSMITTAL DATE: March 17, 2010 1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan until all zoning comments or concerns have been addressed. 2. Zoning has reviewed the building plans and it appears they match the development package. Until the development package has been approved Zoning cannot approve the building plans. 3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved and stamped Development Package. Additional comments may be forthcoming. If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956 RESUBMITTAL OF THE FOLLOWING IS REQUIRED: |
03/18/2010 | RONALD BROWN | BUILDING-COMMERCIAL | REVIEW | Approved | |
03/24/2010 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Approved | |
03/25/2010 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | Clarify the water type being used for the hose bibb located on the North side of building #7; it is shown as both DCW (Stack and Riser Diagram) and as ICW (Plumbing Floor Plan). If the ICW piping is intended to be for industrial use only, label the line to the hose bibb as ICW and specify the appropriate labeling for the hose bibb as non-potable water. Reference: Section 601.2.2, UPC 2006. |
03/25/2010 | ROBERT SHERRY | WATER | REVIEW | Denied | Provide the size of the existing water meter that supports the new 150 GPM demand and its new pressure drop. Reference: Reference: Section 610.1, UPC 2006. |
03/29/2010 | RAY MAJUTA | ELECTRICAL-COMMERCIAL | REVIEW | Denied | See comments for Activity # T10CM00251, Ray T Majuta, PDSD, City of Tucson, 3/29/10 |