Permit Number: T10BU01448
Parcel: 116241110

Review Status: Completed

Review Details: RESUBMITTAL - GRADING

Permit Number - T10BU01448
Review Name: RESUBMITTAL - GRADING
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
12/07/2010 DAVID RIVERA ZONING REVIEW Approved
12/10/2010 ELIZABETH EBERBACH ENGINEERING REVIEW Approved TO: Chelsea Marshall L.A., Wheat Scharf Assoc.
SUBJECT: Sentinel Peak Regional Natural Resource Park improvements Resubmittal Engineering Review
LOCATION: 1501 W SENTINEL PEAK RD, T14S R13E Secs14 & 15, Ward 1
REVIEWER: Elizabeth Leibold, P.E.
ACTIVITIES: T10CM02603 (site plan), T10BU01448 (grading plan)
FLOODPLAIN: Balanced Basin Management Plan, FIRM 2855K

SUMMARY: The subject property and proposed phased improvements include ramada structures, removal of some existing park features, pedestrian drop-off area, shaded rest areas, check dams and micro basins, and other park features to accommodate for the proposed Sentinel Peak Regional Natural Resource Park. Engineering Division of the City of Tucson Development Services Department has received and reviewed the resubmittal package and recommends approval.

The following 11 conditions apply to grading permit T10BU01448:
1) Call for Pre-construction meeting once grading activity is expected to start. For a PDSD Engineering Inspection, call IVR (740-6970), or schedule with a Customer Service Representative at Planning & Development Services Department, or contact DSD Engineering at 837-4888, or schedule inspections online at: http://www.ci.tucson.az.us/dsd/Online_Services/Online_Permits/online_permits.html
2) Call PDSD Engineering for special Inspections during the any toedowns and other subsurface improvements. Inspections will also be needed for the completion of the resin-stabilized DG paths, trail signage, and the check dams to be placed within existing small rivulets where stormwater collection for natural-looking water harvesting
3) See also T10CM02603.
4) Constructed slopes shall not exceed 2:1(H:V) grades without a geotechnical report.
5) There shall be no disturbance outside of approved grading limits.
6) In order to provide inspection clarification and prevent onsite vehicular or pedestrian traffic conflicts, temporary traffic controls may be needed to clarify between continued public uses/access and construction access / maneuverability. Install construction access only signage, or other controls, if/as needed.
7) No storage or placement of construction material and/or vehicles within waterharvesting areas. The temporary material or vehicle staging / stockpile area, and designated washout locations shall not be located in or near water harvesting areas. Staging area shall be designated prior to commencement of construction, and shall not exceed 3,000 square feet.
8) Any revisions to the Grading Plan must be reviewed by the PDSD Engineering Engineer and may include discussion, details, or, a revised grading plan. Call PDSD Engineering at 791-5550 to discuss any revisions.
9) Permanent erosion control is required on all disturbed areas, in the form of vegetative cover, gravel, resin-stabilization, a sized decorative rock, and/or other controls, or as shown on the plans.
10) If grading construction is expected to last longer than the expiration date of the grading permit, contact PDSD to renew/extend the Grading Permit. If Final Grading Inspection has not been completed before the Grading Permit expires, and the permit has not been renewed, additional fees and reviews may be required. Requests for grading permit extensions are found online and may be submitted to Planning & Development Services Department (attn: Claudia Buford), prior to grading permit expiration date, for consideration of grading plan extension approval.
11) As-builts are required to be submitted under the activity number T10BU01448 to the permit clerks. As-builts shall include: completed trail with as-built spot elevations showing no more than 5% longitudinal slopes. The documents will be reviewed and then if acceptable, a copy will be provided to the PDSD Engineering Inspector for final grading inspections. For Grading Permit Project Closure documentation, submit: one copy of original approved grading plans, 2 copies of as-builts, and a substantial completion letter for the project.

I can be reached at 837-4934 if you have questions.

Elizabeth Leibold, P.E., CPM, CFM
Civil Engineer
Engineering Division
Planning & Development Services Department

Final Status

Task End Date Reviewer's Name Type of Review Description
12/03/2012 SUE REEVES APPROVAL SHELF Completed
12/03/2012 SHANAE POWELL OUT TO CUSTOMER Completed