Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL - GRADING ALL
Permit Number - T10BU00665
Review Name: RESUBMITTAL - GRADING ALL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
04/27/2010 | DAVID RIVERA | ZONING | REVIEW | Denied | Zoning has reviewed the grading plan but cannot approve it at this time. While the grading plan matches the site plan the site plan has not been approved and until all reviewers approve the site plan the grading plan cannot be approved by zoning. |
04/28/2010 | LOREN MAKUS | ENGINEERING | REVIEW | Denied | T10CM00576 April 30, 2010 1. Revise the plan to indicate that it is the grading plan for the project rather than the "Conceptual Grading Plan." 2. Since the two phases involve more than one acre of disturbed area, a stormwater pollution prevention plan will be required for the entire project. 3. The SWPPP must meet all of the requirements of the ADEQ stormwater construction permit including the identification of all operators. Additional comments may be forthcoming once these comments have been addressed. Loren Makus, EIT Senior Engineering Associate |
05/12/2010 | ANDREW CONNOR | NPPO | REVIEW | Approv-Cond |