Plan Number: T09PI00011
Parcel: Unknown

Review Status: Completed

Review Details: PIA SUBMITTAL

Plan Number - T09PI00011
Review Name: PIA SUBMITTAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
04/06/2009 TAMI HAUSER UTILITY CLEARANCES COT STREETS DIVISION Denied PLEASE SUBMIT UTILITY CLEARANCE LETTERS.
04/06/2009 TAMI HAUSER UTILITY CLEARANCES COT WATER NEW DEVELOPMENT Denied PLEASE SUBMIT UTILITY CLEARANCE LETTERS.
04/06/2009 TAMI HAUSER UTILITY CLEARANCES PC WASTEWATER MGMT Denied PLEASE SUBMIT UTILITY CLEARANCE LETTERS.
04/06/2009 TAMI HAUSER UTILITY CLEARANCES QUEST COMMUNICATION Denied PLEASE SUBMIT UTILITY CLEARANCE LETTERS.
04/06/2009 TAMI HAUSER UTILITY CLEARANCES TUCSON ELECTRIC POWER CO Denied PLEASE SUBMIT UTILITY CLEARANCE LETTERS.
04/06/2009 TAMI HAUSER UTILITY CLEARANCES COX COMMUNICATION Denied PLEASE SUBMIT UTILITY CLEARANCE LETTERS.
04/06/2009 TAMI HAUSER UTILITY CLEARANCES SOUTHWEST GAS CORP Denied PLEASE SUBMIT UTILITY CLEARANCE LETTERS.
04/06/2009 TAMI HAUSER UTILITY CLEARANCES EL PASO NATURAL GAS Denied PLEASE SUBMIT UTILITY CLEARANCE LETTERS.
04/06/2009 TAMI HAUSER UTILITY CLEARANCES KINDER MORGAN ENERGY Denied PLEASE SUBMIT UTILITY CLEARANCE LETTERS.
04/16/2009 GARY WITTWER DOT LANDSCAPE REVIEW Denied Submit a copy of your approved NPPO plan.
Submit a copy of your site irrigation plans.
(submit a copy of your paper reduction plan)
05/04/2009 LANCE PETERSON DOT STREET MAINTENANCE REVIEW Approv-Cond We have reviewed this plan and have no concerns as long as there is no landscaping to be maintained by the city.

HP & PR
05/06/2009 JOSE ORTIZ DOT TRAFFIC REVIEW Denied May 6, 2009
ACTIVITY NUMBER: T09PI00011
PROJECT NAME: Atterbury Wash Plans
PROJECT ADDRESS: 11311 E Mary Ann Cleveland Wy
PROJECT REVIEWER: Jose E. Ortiz PE, Traffic Engineer

Resubmittal Required: Traffic Engineering does not recommend approval of the PIA Plan; therefore a revised PIA Plan is required for re-submittal. The following items must be revised or added to the plan.

1. Include a response letter with the next submittal that states how all comments have been addressed.

2. See redlines on the submitted drawings and address the additional redline comments. During the next submittal please re-submit the roll of redlines for back checking purposes.

3. Install street name signs at the proposed roadway intersections per PCDOT & TDOT Signing Manual (2002) Chap 5-11, 5-12, and Chap 9-2.

4. Place the PIA Case number on the cover sheet.

5. Add the following Signing General Notes 5(a) & 5(b) per PCDOT & TDOT Signing Manual (2002) (Chapter 1, Sheet 12) to the Plans.

6. Add the following Pavement Marking/Striping General Notes to the Plans:

'ALL STREET SIGNAGE TO BE COORDINATED WITH C.O.T. TRAFFIC ENGINEERING CALL 791-4259 A MINIMUM OF 48 HOURS PRIOR TO THE INSTALLATION OR REMOVAL OF ANY SIGNAGE OR STRIPING. ALL REQUIRED SIGNAGE WILL BE INSTALLED AT THE CONTRACTOR'S EXPENSE.. USE 2" SQUARE-TUBE POST AND SQUARE TUBE POST FOUNDATIONS FOR SIGNING.

'ALL NON-SIGNALIZED INTERSECTION STREET NAMES MUST HAVE E-W BLOCK NUMBER ADDRESSES FOR E-W ROADWAYS AND N-S BLOCK NUMBER ADDRESSES FOR N-S ROADWAYS.'

'THE CITY SHALL NOT BE LIABLE FOR ANY ERRORS AND/OR OMISSIONS ON THESE PLANS. ITEMS NOT MEETING CITY STANDARDS SHALL BE REPAIRED/REPLACED BY THE DEVELOPER/CONTRACTOR AND AT NO COST TO THE CITY.'


If you have any questions, I can be reached at 791-4259 x76730 or Jose.Ortiz@tucsonaz.gov
05/07/2009 RICHARD LEIGH DOT ENGINEERING REVIEW Denied 6 May 2009

SUBJECT: Mountain Vail Estates, Part "C", Public Improvements, PIA T09PI0011

PROJECT REVIEWER: Richard Leigh, DOT, Permits and Codes Section

RESUBMITTAL REQUIRED: Permits and Codes Section has reviewed the PIA Plan and does not recommend approval of the PIA Plan at this time. The following comments need to be addressed in the next submittal.

1. Include the plan number "I-2009-010" in title block of each sheet.

2. Include Development Services Department PIA activity number "T09PI00011"on cover sheet.

3. Sheet 3, Detail 1/3: Indicate proposed roadway cross slope.

4. Sheet 3, Detail 2/3: Indicate proposed roadway cross slope.

5. Sheet 3, Detail 5/3: Indicate a minimum 5'x 5' landing for the proposed ramps

6. Sheet 4, Detail 5/4: Delineate Right-of-Way.

7. Sheet 4, Detail 7/4: Indicate proposed roadway cross slope.

8. Sheet 4, Detail 7/4: Provide additional cross section, plan view and clarify details of catch basin top.

9. Clearly show where the project's construction will end at Atterbury Was Way

10. Provide post barricades and appropriate signage where the pavement terminates for subdivision phasing to restrict vehicular traffic.

11. Placement of private irrigation facilities within the right-of-way will require a private utility easement. Please contact the COT Real Estate Division for information on acquiring an easement. Additionally, private irrigation facilities must meet COT adopted standards. Note the following requirements to any proposed irrigation in the right-of way.

q Schedule 80 sleeving.
q Marking tape.
q Minimum 18" depth.
q Mark/stamp on curb - IS (Irrigation System) and/or placard at back of curb
q Sleeves must be in a recorded easement (easement width is dependent on what is needed for installation and/or repairs).
q Sleeve should extend beyond the right-of-way (into private property), unless otherwise approved by TDOT.

12. Verify that a 2' minimum set back is provided from the hinge point of any cut and fill slope on private property and the property line (City of Tucson Development Standard 11-09.0).

13. Add the following notes to the General Storm Drain Notes:

q Drainage pipe shall conform to PC/COT SSPI Section 501or as directed by the engineer.
q Pipe bedding shall conform to PC/COT Standard Detail 108.

14. Provide barricade railing along the right-of-way of any slope steeper than 4:1 and deeper than two (2) feet. Note ending and beginning of any proposed barricade railing.

15. Verify that the cross slopes for pedestrian cross walk areas does not exceed 2%.

Refer to redline plans for additional comments and comment details.

If you have any questions, I can be reached at 837-6647 or Richard.Leigh@tucsonaz.gov
05/15/2009 TAMI HAUSER PIA COORDINATOR CUSTOMER CALLED Completed
05/15/2009 TAMI HAUSER PIA COORDINATOR OUT TO CUSTOMER Completed