Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Plan Review Detail
Review Status: Completed
Review Details: PIA RESUBMITTAL
Plan Number - T09PI00003
Review Name: PIA RESUBMITTAL
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 04/08/2009 | TAMI HAUSER | UTILITY CLEARANCES | COT STREETS DIVISION | Denied | PLEASE SUBMIT UTILITY CLEARANCE LETTERS. |
| 04/08/2009 | TAMI HAUSER | UTILITY CLEARANCES | COT WATER NEW DEVELOPMENT | Denied | PLEASE SUBMIT UTILITY CLEARANCE LETTERS. |
| 04/08/2009 | TAMI HAUSER | UTILITY CLEARANCES | PC WASTEWATER MGMT | Denied | PLEASE SUBMIT UTILITY CLEARANCE LETTERS. |
| 04/08/2009 | TAMI HAUSER | UTILITY CLEARANCES | QUEST COMMUNICATION | Denied | PLEASE SUBMIT UTILITY CLEARANCE LETTERS. |
| 04/08/2009 | TAMI HAUSER | UTILITY CLEARANCES | TUCSON ELECTRIC POWER CO | Denied | PLEASE SUBMIT UTILITY CLEARANCE LETTERS. |
| 04/08/2009 | TAMI HAUSER | UTILITY CLEARANCES | COX COMMUNICATION | Denied | PLEASE SUBMIT UTILITY CLEARANCE LETTERS. |
| 04/08/2009 | TAMI HAUSER | UTILITY CLEARANCES | SOUTHWEST GAS CORP | Denied | PLEASE SUBMIT UTILITY CLEARANCE LETTERS. |
| 04/08/2009 | TAMI HAUSER | UTILITY CLEARANCES | EL PASO NATURAL GAS | Denied | PLEASE SUBMIT UTILITY CLEARANCE LETTERS. |
| 04/08/2009 | TAMI HAUSER | UTILITY CLEARANCES | KINDER MORGAN ENERGY | Denied | PLEASE SUBMIT UTILITY CLEARANCE LETTERS. |
| 05/08/2009 | RICHARD LEIGH | DOT ENGINEERING | REVIEW | Denied | 8 May, 2009 SUBJECT: Valencia Road and Nogales Highway Offsite Improvements for Circle K, PIA T09PI0003 PROJECT: REVIEWER: Richard Leigh, DOT, Permits and Codes Section RESUBMITTAL REQUIRED: Permits and Codes Section has reviewed the PIA Plan and does not recommend approval of the PIA Plan at this time. The following comments need to be addressed in the next submittal. 1. The proposed channel, on the southwest corner of Valencia Rd and Nogales Highway, is not acceptable. Existing drainage patterns must be maintained. According to the existing topography, it appears that these flows originally entered the project site at a low point at approximately Sta. 3185+61, LT. (Nogales Highway). Off-site flows should continue to enter the subject site at this point, thus eliminating the need for the proposed channel Any proposed drainage structures will require supporting hydrologic and hydraulic analysis submitted for review. 2. Provide a concrete bus pad based on ADOT Standard Detail C-05-50. Depict and call out in plan view and provided complete details. 3. Include recordation information of Final Plat on cover sheet. 4. Provide safety railing per COT Development Standards DS 3-01.4.2.F for the ramp leading from the bus pad area to on-site. If you have any questions, I can be reached at 837-6647 or at Richard.Leigh@tucsoz.gov |
| 05/12/2009 | JOSE ORTIZ | DOT TRAFFIC | REVIEW | Denied | May12, 2009 ACTIVITY NUMBER: T09PI00003 PROJECT NAME: Circle K PROJECT ADDRESS: 530 E Valencia Rd PROJECT REVIEWER: Jose E. Ortiz PE, Traffic Engineer Resubmittal Required: Traffic Engineering does not recommend approval of the PIA Plan; therefore a revised PIA Plan is required for re-submittal. The following items must be revised or added to the plan. 1. Include a response letter with the next submittal that states how all comments have been addressed. 2. See redlines on the submitted drawings and address the additional redline comments. During the next submittal please re-submit the roll of redlines for back checking purposes. If you have any questions, I can be reached at 791-4259 x76730 or Jose.Ortiz@tucsonaz.gov |
| 05/20/2009 | TAMI HAUSER | PIA COORDINATOR | CUSTOMER CALLED; PLANS @ AMBASSADOR | Completed | |
| 05/20/2009 | TAMI HAUSER | PIA COORDINATOR | OUT TO CUSTOMER | Completed |