Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL TI
Permit Number - T09CM03199
Review Name: COMMERCIAL TI
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
01/25/2010 | RAY MAJUTA | ELECTRICAL-COMMERCIAL | REVIEW | Denied | Project: T09CM03199 T I Retail Provide total load caculations which include new 400 amp panel plus other existing loads on this service. Ray T Majuta,PSDS,City of Tucson Elect Pln Ck 1/25/10 |
01/25/2010 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Comment not addressed. Provide a vacuum relief for storage-type water heaters located above any fixture outlets. Reference: Section 608.7, UPC 2006. 2. Comment not addressed. Show the return piping for recirculated hot water on the plans. If no recirculated hot water is to be provided with this activity, revise the detail to show the relevent design. Reference: Section 103.2.3, UPC 2006. 3. Provide upper terminal cleanouts on horizontal drainage pipes exceeding 5 feet in length (horizontal drain lines serving sinks require cleanouts regardless of length). Reference: Section 707.4, UPC 2006. 4. Provide vents for the floor drains. 5. Clarify the design for the gas piping. If the new rooftop units do not have the same (or lower) gas requirement as the units being replaced, show the complete gas piping system, complete with all loads and developed pipe lengths. |
01/25/2010 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. The condensate drains may not terminate over a roof drain unless the roof drain itself discharges to a location that will absorb all of the water with no surface runoff.. Reference: Section 307.2, IMC 2006 as amended by the City of Tucson and Section 814.0, UPC 2006. 2. Revise the ventilation calculations per Section 403.3, IMC 2006. Reference: Section 401.2, IMC 2006. 3. Materials exposed in plenums shall conform to Section 602.2.1, IMC 2006. 4. Specify the minimum resistance (R-value) of the duct insulation to be used on this project. Reference: Section 503.2.7, IECC 2006, as amended by the City of Tucson. 5. Clarify the number of rooftop units to be used for this activity. Four units are scheduled but only three are shown on the plans. Also, confirm the input heating capacity of the scheduled rooftop units. 6. The minimum font size is 3/32". |
01/26/2010 | GBONILL1 | FIRE | REVIEW | Needs Review | |
01/26/2010 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Approved |