Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL - TI ALL
Permit Number - T09CM02738
Review Name: RESUBMITTAL - TI ALL
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 02/23/2010 | STEVE SHIELDS | ZONING | REVIEW | Denied | DSD TRANSMITTAL FROM: Steve Shields Lead Planner PROJECT: 2945 E. Speedway T09CM02738 Building Plan (3rd Review) TRANSMITTAL DATE: February 18, 2010 1. The building plans have been reviewed by Zoning Review Section but cannot approve the plan until all zoning comments or concerns have been addressed. 2. Zoning can not approve the building plan until the site plan is approved by all PDSD agencies. 3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved and stamped site plan. Additional comments may be forthcoming. If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956 C:\planning\grading\t09cm02738.doc RESUBMITTAL OF THE FOLLOWING IS REQUIRED: |
| 02/23/2010 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Approved | |
| 02/23/2010 | BIANCA RAMIREZ | ENGINEERING | REVIEW | Denied | 2/18/10 Reviewed revised comments over the counter with Lisa B. All comments appear to have been addressed. Unable to approve until DDO has been reviewed and approved. Verify site revision in regard to letter. Bianca |
| 02/24/2010 | MARTIN BROWN | FIRE | REVIEW | Approved | |
| 03/01/2010 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Comment not resolved. The plumbing plan and the kitchen plan show different gas loads and different equipment; coordinate the gas piping design with the kitchen design and determine the actual equipment being installed with the correct gas loads. Reference: Sections 103.2.3 and 1217.0, UPC 2006. 2. Comment not resolved. Show the flue height and show the flue termination. Reference: Sections 103.2.3 and 510.6.2, UPC 2006. 3. Comment not resolved. The ½" branch piping sizes called out for the urinal flush valve will result in water velocities greater than 8 FPS. Limit the water velocity to less than 8 FPS for the copper piping. Reference: Section A 6.1, UPC 2006 and IS 3-2003, Section 2.6. 4. Comment not resolved. Provide a vent for each fixture trap (either an air admittance valve or a conventional vent). Provide a vent for the grease interceptor, as shown in detail 8/P2. Reference: Sections 901.0 and 910.1, UPC 2006. Note: see also Section 801.3, UPC 2006. 5. Comment not addressed. Provide roof drainage calculations and plans. All roof areas shall be drained by roof drains, scuppers, or gutters. Show also, how the drainage for the existing roof is being affected by the new roofs. Reference: Section 1101.11.1, UPC 2006. |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 03/03/2010 | GERARDO BONILLA | OUT TO CUSTOMER | Completed |
| 03/03/2010 | SUE REEVES | REJECT SHELF | Completed |