Permit Number: T09CM02694
Parcel: 135074390

Review Status: Completed

Review Details: COMMERCIAL NEW

Permit Number - T09CM02694
Review Name: COMMERCIAL NEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
10/07/2009 DAVE MANN FIRE REVIEW Denied Please include the following fire sprinkler design criteria to the plans.
1. Flow data (static pressure, residual pressure, GPM)
Available from the Fire Department (520) 791-3234
2. The standard to be used in development of sprinkler system. (NFPA 13, NFPA 13R, or NFPA 13D)
3. The hazard classification of the building, including any special hazards.
4. The density required of the water supply.
10/09/2009 RONALD BROWN BUILDING-COMMERCIAL REVIEW Denied 1. Provide foundation plan references to all footing/pier details used shown on sheet AB2 of 2.
2. Calculations provided for the two footing/piers of the left side of sheet AB2 of 2 but they are incomplete for the footing/pier shown on the right side of the sheet. If this detail is not used, please delete it. If it is used please reference to foundation plan and provide complete calculations.
10/09/2009 RONALD BROWN ZONING HC REVIEW Passed
10/15/2009 GERRY KOZIOL WWM REVIEW Passed
10/16/2009 RAY MAJUTA ELECTRICAL-COMMERCIAL REVIEW Approved
10/23/2009 TERRY STEVENS ZONING REVIEW Denied 10/23/2009

Development Services Department
Zoning Review Section

Terry Stevens
Lead Planner

Comments:

1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed.

2. Zoning could not verify that the building plan was in compliance with the approved development plan. Please submit two copies of the approved and stamped development, landscape, and NPPO plans with the next building plan submittal.

3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved site/development plan. Additional comments may be forthcoming.
10/26/2009 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Passed
10/26/2009 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Approved
10/26/2009 ROBERT SHERRY WATER REVIEW Passed
10/28/2009 LAITH ALSHAMI ENGINEERING REVIEW Approved

Final Status

Task End Date Reviewer's Name Type of Review Description
11/06/2009 CPIERCE1 OUT TO CUSTOMER Completed
11/06/2009 SUE REEVES REJECT SHELF Completed