Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL TI
Permit Number - T09CM02020
Review Name: COMMERCIAL TI
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 07/30/2009 | GERRY KOZIOL | WWM | REVIEW | Approved | |
| 07/30/2009 | DAVE MANN | FIRE | REVIEW | Approved | |
| 08/04/2009 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Approved | |
| 08/05/2009 | ERIC NEWCOMB | ZONING HC SITE | REVIEW | Approved | |
| 08/07/2009 | RMYERS1 | WATER | REVIEW | Denied | 1. Provide the size of the existing water meter and the total connected water demand that will result from the addition of this activity. Include the demand due to the three evaporative coolers in addition to the plumbing fixtures. Reference: Sections 610.1 and 610.2, UPC 2006. 2. Reduced pressure backflow prevention assemblies are required at the water meter for multi-use commercial buildings. Show the size and location of the reduced pressure backflow prevention assembly on the drawing. Reference: Section 103.2.3, UPC 2006 and COT Ordinance 9976, http://www.tucsonaz.gov/water/docs/backflow-ord.pdf |
| 08/07/2009 | RICK MYERS | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Clarify suite number. Permit shows suite "B" as unit #150. Plan shows suite "B" as being unit 200. 2. See Fixture Schedule on sheet P-1. Use the WSFU and DFU equivalents as shown on Table 6-5 and Table 7-3, 2006 UPC. 3. Provide a site utility plan for reference. 103.2.2 2006 UPC. Include water meter size, available pressure, yardline size, and water sizing for all applicable fixtures. 4. Clarify the plumbing notes on sheet P-1 showing type "K" below slab, and type "L" above grade, with the general notes on sheet P-2 which shows type "L" below slab, and type "M" above grade. 5. Sheet P-1 shows vents may be No-Hub, sch.40 PVC, or sch.40 ABS. Sheet P-2 shows vents to be sch.40 PVC. Clarify materials to be used. 6. The point of use water heater cut sheet provided with the drawings (Ariston Electric Point-of-Use Mini-Tank) requires a temperature and pressure relief, expansion tank, and shut-off valves. Provide a detail of the water heater installation. Reference: Sections 103.2.3, 605.5, 608.3, and 608.7 UPC 2006. 7. Provide information to show how the outlet temperature of the hot water is to be limited to 110 degrees at the lavatory. Reference: Section 413.1, UPC 2006 and Section 504.3, IECC 2006. 8. The specified lavatory faucets are designed for a flow rate of 2.2 GPM. According to ARS Title 45, Chapter 1, Article 12, the maximum flow rate for lavatory faucets shall be no more than an average of one-half gallon of water per minute at a pressure of eighty PSI or they shall be equipped with a mechanism that causes the faucet to close automatically after delivering no more than one-fourth gallon of water. Reference: Section 402.1, UPC 2003, as amended by the State of Arizona. 9. Clarify the size and manner of installation of the 2-1/2" cleanout shown at the junction of the building drain and the building sewer south of this suite. Reference: Sections 311.7, 707.6, and 707.11, UPC 2006. |
| 08/12/2009 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | The legend on sheet M-1 shows a "new exhaust fan" and the submitted cut sheets include one for a Broan ceiling-mounted fan. Show the location for the fan and provide balancing data for the fan. Reference: Sections 106.3.1 and 403.3, IMC 2006. |
| 08/20/2009 | RAY MAJUTA | ELECTRICAL-COMMERCIAL | REVIEW | Denied | See comments for Activity # T09CM02021, Ray T Majuta Elect Pln Ck 8/22/09 |
| 08/26/2009 | STEVE SHIELDS | ZONING | REVIEW | Denied | DSD TRANSMITTAL FROM: Steve Shields Lead Planner PROJECT: Cupps Industrial Supply T09CM02020, T09CM02021, T09CM02023, T09CM02027 Building Plan (1st Review) TRANSMITTAL DATE: August 26, 2009 1. The building plans have been reviewed by Zoning Review Section but cannot approve the plan until all zoning comments or concerns have been addressed. 2. Zoning could not verify that the building plan was in compliance with the approved site plan. Please submit two copies of the approved and stamped site plan with the next building plan submittal. 3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved and stamped site plan. Additional comments may be forthcoming. If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956 C:\planning\grading\t09cm02020.doc RESUBMITTAL OF THE FOLLOWING IS REQUIRED: |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 08/26/2009 | CINDY AGUILAR | OUT TO CUSTOMER | Completed |
| 08/26/2009 | SUE REEVES | REJECT SHELF | Completed |