Permit Review Detail
Review Status: Completed
Review Details: RESIDENTIAL BLDG/WWM
Permit Number - T09CM01827
Review Name: RESIDENTIAL BLDG/WWM
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 07/29/2009 | GERRY KOZIOL | WWM | REVIEW | Approved | |
| 08/19/2009 | RBROWN1 | BUILDING-RESIDENTIAL | REVIEW | Denied | 1. Show the location of attic access min. 22"x30", R807. 2. Note that the max window sill height is 44". 3. On the foundation plan, please note grade away from foundations shall fall min 6" within the first 10’, R401.3. 4. Structural Foundation and Framing Plans: a. Provide a detail showing the existing foundation to the new slab condition. b. The far North West end of the new ridge beam requires additional vertical support from the wall below. This is now aconsintrated load that may niot be accomodated by the existing roof joists. 5. Concerning Exterior Elevations; a. Please provide the third elevation. b. Specify height above grade for finished floor,windows, doors, exterior walls, rooflines, porches and etc. c. Specify roof slope and roofing type, grade of materials, and method of installation, R905, Shingle: two-layer underlayment for low-slope (2:12 to 4:12), R905.2.7. 6. Please provide a detail and specification of how the brick tile veneer is to be applied to the framing. 7. Please show a detail of the non-bearing interior wall conditions (floor and rafter/joist connections & gaps). 8. The following FLOOR PLAN NOTES are not relative to this project. Please remove these and any others that have nothing to do with this project: 1, 10, 15, and 19. 9. Electrical Plans: a. I'm not sure what the intent is for the electrical panel distribution system. Notes on the electrical plan indicate a new electrical panel and meter where as the panel schedule shows a new 200A panel. Obviously, the location is new as it is shown on the back of the new addition. Where is the original panel located? If this panel is to be relocated as indicated on the floor plan, please describe, detail and provide further electrical design for the extension of the existing branch circuits to the new location. If the existing panel is to remain as a sub panel, please show electrical design accordingly. a. Provide an electrical riser diagram with grounding method and bonding to metallic piping, E3303, E3507. Gas lines shall not be used as the primary grounding method, E3508. b. Provide riser diagrams for sub-panels with feeder conductors, conduit sizes, and over-current protection (with appropriate correction factors), E3605.5. c. Provide electrical load calculations for determining the service panel size, E3502.2.; Provide feeder load calculations for sub-panels (40% demand factor may not be applied), E3604.3; Provide a panel schedule: panel size, circuit numbers, ampacity, and wire sizes, E3304.11, E3606.2. 10. Panelboards may not be located in clothes closets or bathrooms, E3305.4. 11. Indicate location of all mechanical equipment disconnect switches, E4001.5. 12. Plumbing: a. Plumbing shall comply with 2006 UPC with state amendments (AZ State plumbing code). The plans should reference this code, or appeal to the Building Official for alternate design approval. b. Fixture unit schedule required for the entire property (including existing) UPC Tables 6-5 and 7-3. c. Provide the maximum developed length of water line from the meter the furthest appliance served, and the diameter of the water line, UPC Table 6-6. d. Show condensate discharge line for HVAC unit on roof. Do not discharge into a plumbing vent. e. Provide a gas line isometric and size the supply pipe for the connected demand. Include the length of line and BTU demand for each appliance, size of each branch, total demand, and total developed length from meter to the most remote appliance on the system, UPC 1217.0 Table 12-8. Sleeves are required when a gas line passes through concrete, UPC 1211.1.5. Any underground gas piping beneath buildings shall be encased in an approved sealed & vented conduit, UPC 1211.1.6. 13. Mechanical: a. Provide an equipment specification list, M1302.1. b. Show the condensate line and secondary for HVAC unit, M1411.3 14. Provide a note requiring the insulation certificate shall be posted in the electrical distribution panel before final inspection, N1101.8. END OF REVIEW |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 08/21/2009 | CPIERCE1 | OUT TO CUSTOMER | Completed |
| 08/21/2009 | SUE REEVES | REJECT SHELF | Completed |