Permit Number: T09CM01698
Parcel: 141019170

Review Status: Completed

Review Details: RESUBMITTAL

Permit Number - T09CM01698
Review Name: RESUBMITTAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
08/12/2009 ERIC NEWCOMB ZONING HC SITE REVIEW Approved
08/12/2009 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Approved
08/19/2009 RICK MYERS PLUMBING-COMMERCIAL REVIEW Denied 1. See sheet P4.2 detail 10. Reference 909.0 2006 UPC: Traps for island sinks and similar equipment shall be roughed in above the floor... 2. 909.0 2006 UPC continues; the return vent shall be connected to the horizontal sink drain immediately down stream of the vertical fixture drain. The return vent shall be connected to the horizontal drain through a wye branch fitting, and shall, in addition, be provided with a foot vent taken off the vertical fixture vent by means of a wye branch immediately below the floor and extended to the nearest partition. 3. Floor sinks shall not be located inside/under cabinets. Reference 804.1 2006 UPC. ....and shall be located where they are readily accessible for inspection and cleaning. 4. See sheet P4.2 detail two. The City of Tucson requires a reduced pressure backflow preventer for carbonators. Note: If the soda machine dispenses potable water, and/or other beverages that are not carbonated, a separate backflow device is required for each. 5. See sheet P3.1. At the water service connection, the plan shows 21/2" CW.(See Civil Plans for continuation). Sheet 6 of 16 of the development package shows a 2" meter, and a 2" yardwater piping to the building. Coordinate Site Water with sheet P3.1 6. Sheet 4.1 detail 3 refers to the gate valve detail 2/P3.1- there is no detail 2 on sheet P3.1. 7. Show how the lavatories meet the 2006 IECC requirement for maximum delivery of 110 degrees. 8. Waterless urinals- Reference 601.1 2006 UPC; Each plumbing fixture is to have an adequete supply of potable running water.... If Civano Development requirements dictate waterless urinals, then provide the petition of appeal as required by the City of Tucson.
08/24/2009 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Denied 1. Provide information on the sequence of operation for the restroom exhaust to show that recirculation of the air from the restroom will not occur. Reference: Section 403.2.1, IMC 2006.
2. Comment not resolved; the reply to the original comment stated that the dampers would be from detail 1/M3.2. They are still there but now they are clouded. Show how the installation of both a balance damper and a barometric damper in the grease duct (detail 1/M3.2) will prevent the accumulation of grease within the duct. Reference: Section 506.3.7, IMC 2006. Note that the detail and the kitchen hood schedule shown on sheet M1.1 also contradict the duct size and the exhaust air flow noted in the calculations shown on sheet M3.2.
3. The installation of the future Type I hood will require a separate permit.
08/26/2009 LAITH ALSHAMI ENGINEERING REVIEW Denied Laith Alshami, Engineering and Floodplain Review, 08/26/2009,

The Site Plan can not be approved until the development package has been approved.
09/04/2009 RAY MAJUTA ELECTRICAL-COMMERCIAL REVIEW Approved