Permit Number: T09CM01432
Parcel: 11502430A

Address:
216 E LEE ST

Review Status: Completed

Review Details: RESIDENTIAL BLDG/WWM

Permit Number - T09CM01432
Review Name: RESIDENTIAL BLDG/WWM
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
08/04/2009 GERRY KOZIOL WWM REVIEW Denied need to connect exterior bar sink to sewer with 2-way bypass valve to landscape- need 13 greywater conditions on drawings
08/28/2009 RONALD BROWN BUILDING-RESIDENTIAL REVIEW Denied SITE PLAN
1. No gas service shown to residence.
2. Utility Room addition is not shown on site plan. Please show.
FLOOR PLAN
3. Tub/shower enclosures require nonabsorbent wall surface min. 6’ above the floor and fiber-cement board backing, R307.2, R702.4.2.
4. Location of tempered glass, R308.4.
a. Within: 18' of the floor, 24"of doorways, less than 60" above tub/shower floors
b. Adjacent to stairways and landings (36"of a walking surface, less than 60" above)
EXTERIOR ELEVATIONS
5. Please provide elevations of the utility room expansion.
6. For thin-coat stucco systems, indicate the ICBO #, system name, and vapor barrier, R703.6.
ELECTRICAL PLAN
7. Please follow Chapter 41 of the IRC for all electrical installations in the Power Pool enclosure as per Sections E4103.4.4 and .4.5.
8. Insure N3R rating for all outdoor electrical devices and panels.
9. Bathrooms require a separate 20-amp circuit with receptacles within 3’ of the basin, E3801.6.
10. GFCI protection required in bathrooms, kitchens, unfinished basements, garages/carports, exterior
receptacles, and within 6’ of a wet bar or sink, E3802.
PLUMBING PLANS
11. Fixture unit schedule required for the entire property (including existing) UPC Tables 6-5 and 7-3.
12. Provide the maximum developed length of water line from the meter the furthest appliance served, and
the diameter of the water line, UPC Table 6-6.
13. Water conservation requirements: Water closets = 1.6 gallons per flush, Sinks/ Showerheads = 3 gpm,
UPC State Amend. 45-312.
14. Provide a gas line isometric and size the supply pipe for the connected demand. Include the length of line and BTU demand for each appliance, size of each branch, total demand, and total developed length from meter to the most remote appliance on the system, UPC 1217.0 Table 12-8.
MECHANICAL PLANS
15. Provide mechanical ventilation of the power spa room for humidity control as required by section 303.1 and 303.3
INTERNATIONAL ENERGY CODE
16. Provide a note requiring the insulation certificate shall be posted in the electrical distribution panel before final inspection, N1101.8.
GENERAL
17. Please clarify how the existing building interior masonry, exposed wood trusses, exposed wood roof decks and all exposed metal connectors and metal parts are protected from high humidity and corrosion from chlorine vapors as to meet the IEC requirements of Section 402.5.
18. Please provide a finish schedule of finishes ie: what is F1, B1, W1, ETC shown on finish schedule.

END OF REVIEW

Final Status

Task End Date Reviewer's Name Type of Review Description
08/31/2009 CINDY AGUILAR OUT TO CUSTOMER Completed