Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Active
Review Details: COMMERCIAL TI
Permit Number - T09CM01396
Review Name: COMMERCIAL TI
Review Status: Active
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 01/13/2010 | MARTIN BROWN | FIRE | REVIEW | Denied | Fire Comments: Automatic fire sprinklers are required due to distance from fire hydrant. A new hydrant may be provided instead per IFC 508.5.1 as amended. |
| 11/17/2009 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. Provide calculation and show how ventilation will be provided for the new building areas. Reference: section 401, IMC 2006. 2. Provide energy code compliance calculations (the correct climate zone is Pima County < 4,000 feet). Provide sufficient detail on the drawings to evaluate the energy compliance of the building envelope. The information shall, as a minimum, include U-factors of the envelope systems and fenestration components, along with the R-values of the insulation and the SHGC for the fenestration. Reference: Sections 101.4 and 104.2, International Energy Conservation Code 2006. 3. Clarify the capacity of the proposed roof top A/C unit; it is noted as 3.5-tons and 5-tons but the airflow is 3590 CFM. 4. Show that the roof top unit can provide sufficient heat to maintain a minimum temperature of 68 F on a design heating day (32 F). Reference: Section 309.1, IMC 2006. 5. Show the size, routing, and termination of the condensate drain. Reference: Section 307.2, IMC 2006 and Section 814.0, UPC 2006. 6. Revise the mechanical design as required to avoid using the corridor as a return air duct. Reference: Section 601.2, IMC 2006. 7. Specify the minimum resistance (R-value) of the duct insulation to be used on this project. Reference: Section 503.2.7, IECC 2006, as amended by the City of Tucson. |
| 11/17/2009 | RAY MAJUTA | ELECTRICAL-COMMERCIAL | REVIEW | Denied | Project: T09CM01396 2820 E Fort Lowell Office Plans denied for following: 1. Load calculations provided are Residential format, provide in commercial format. 2. New AC unit on roof show a 60 amp diconnect and provide a service maintance receptacle per 2005 NEC,210.63,if one not already installed. 3. Provide 2006 IECC LIGHT BUdget calculations for lighting. 4. Provide location of service and panel. Ray T NMajuta Elect Pln Ck PDSD City of Tucson 11/17/09 Ray.Majuta@tucsonaz.gov |
| 11/17/2009 | ROBERT SHERRY | WATER | REVIEW | Approved | |
| 11/17/2009 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Denied | 1. GENERAL: COORDINATE THE BUILDING FOOTPRINT BETWEEN WHAT IS SHOWN ON SHEET A-2 AND S2.0. 2. STRUCTURAL CALCULATIONS SHEET 8: THE STRUCTURAL CALCULATIONS NOTE 2X6 WALL STUDS AT 16" OC, WHILE NOTE 7 ON SHEET S2.0 INDICATES 2X4 AT 16" OC. CLARIFY. 3. GENERAL: PROVIDE STRUCTURAL CALCULATIONS FOR THE NEW MECHANICAL UNIT ON THE ROOF (EXCEEDS 300# LISTED ON PLAN). |
| 11/17/2009 | ANY | WWM | REVIEW | Active | |
| 11/17/2009 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Indicate the materials to be used in the proposed plumbing systems for this activity. Reference: Sections 103.2.3, 301.1, 604.0, 701.0, 903.0, 1102.0, and 129.5, UPC 2006. 2. Provide fixture descriptions for all plumbing fixtures. All plumbing fixtures and fittings shall be listed or labeled by a nationally-recognized, accredited conformity assessment company (e.g. UL, ETL, UPC, etc). Reference: Sections 301.1.1 and 401.1, UPC 2006. 3. Provide a specification for the proposed water heater. Reference: Section 103.2.3, UPC 2006. 4. Show how the temperature of the hot water supply to the public lavatories is controlled. Reference: Section 413.1, UPC 2006 and Section 504.3, IECC 2006. 5. Provide a detail of the water heater installation, including the excess pressure relief, expansion tank, recirculation pump and valves. Reference: Sections 103.2.3, 605.5, and 608.3, UPC 2006. 6. Show how the hot water recirculation system complies with Section 504.6, IECC 2006. 7. Show the size, route, and termination of the temperature and pressure relief for the water heater. Reference: Section 103.2.3, UPC 2006. 8. Provide an upper terminal cleanout for the new service sink. Reference: Section 707.4, UPC 2006. 9. Verify that a cleanout exists for the existing and new water closets, sized per Section 707.11, UPC 2006. 10. Provide vent piping of sufficient size to comply with Section 904.1, UPC 2006. |
| 11/17/2009 | ANY | ENGINEERING | REVIEW | Active | |
| 11/17/2009 | ANY | ZONING | REVIEW | Active | |
| 11/17/2009 | ERIC NEWCOMB | ZONING HC | REVIEW | Denied | 1. GENERAL: PROVIDE FULLY DIMENSIONED ARCHITECTURAL PLAN. 2. GENERAL: PROVIDE CODE ANALYSIS ON THE DRAWINGS. 3. GENERAL: PROVIDE ENLARGED PLANS OF THE TWO RESTROOMS, ADDING DIMENSIONS PER ICC/ANSI A117.1-2003. 4. GENERAL: PROVIDE ELEVATIONS OF RESTROOM WALLS INCLUDING ALL ITEMS REQUIRED BY ICC/ANSI A117.1-2003. |
| 11/17/2009 | BETH GRANT | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Approved |