Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL TI
Permit Number - T09CM01232
Review Name: COMMERCIAL TI
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
05/15/2009 | MARTIN BROWN | FIRE | REVIEW | Approved | |
05/19/2009 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Denied | 1. SHEET S-1; CALCULATIONS: CALCULATIONS INDICATE THE 8" TUBE DIMENSION IS IN THE VERTICAL DIRECTION. IS THIS THE CASE? 2. SHEET S-1; SECTION 3: INCLUDE THE NEW TUBE IN THIS SECTION, INDICATING HOW THE TUBES ARE CONNECTED TO THE EXISTING ROOF STRUCTURE. 3. SHEET S-1; PLAN VIEW 2: WHAT ARE THE HORIZONTAL BRACING MEMBER SIZES, AND HOW ARE THEY CONNECTED TO THE TUBE STEEL? 4. SHEET S-2; CALCULATIONS: CALCULATIONS INDICATE THE 6" TUBE DIMENSION IS IN THE VERTICAL DIRECTION. IS THIS THE CASE? 5. SHEET S-2; PLAN 1: INDICATE ON THE PLAN HOW THE TUBES ARE CONNECTED TO THE EXISTING ROOF STRUCTURE. 6. SHEET A-2; DETAIL 15: APPLY IBC SECTION 1109.8 AND ANSI SECTION 308 FOR ACCESSIBILITY TO STORAGE ELEMENTS. ADJUST DETAIL AS REQUIRED. 7. GENERAL: PROVIDE WRITTEN RESPONSES TO ALL PLAN REVIEW COMMENTS. |
05/20/2009 | JOHN WILLIAMS | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Passed | |
05/20/2009 | ERIC NEWCOMB | ZONING HC SITE | REVIEW | Denied | 1. SEE BUILDING COMMENTS. |
05/22/2009 | GERRY KOZIOL | WWM | REVIEW | Denied | need 5th floor credit evaluation |
06/02/2009 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. Clarify the heat pumps being used for this suite; the calculations refer to HP-2 which doesn't appear to be on the plans. 2. Note that the use of ASHRAE Standard 62.1-2004 for ventilation calculations for multiple-zone systems supplied by a single air handler requires the use of the calculations covered by Section 6.2.5, ASHRAE Standard 62.1-2004 to determine the design outdoor air intake. Your balancing data for HP-1 (300 CFM), has added sufficient outside air to cover the greater air flow that would have been shown by the complete calculations. |
06/03/2009 | RMYERS1 | WATER | REVIEW | Approved | |
06/03/2009 | RICK MYERS | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Keynote number above keynote 12 on sheet P-1 detail C is missing. 2. Reference 608.7 2006 UPC, Where a water heater storage tank is located above the fixture outlets, a vacuum relief valve shall be installed. 3. Per Plumbing Plan Notes on sheet P-4, 2.14- Pipe Insulation, subsection "b", please identify size and type of insulation to be used. 4. Per detail 207, on sheet P-3, the temperature and pressure relief drain and the pan drain may not be combined. 5. On sheet P-2, Plumbing Schedule- modify mop sink hot water requirements to include 3/4" hot water supply. Remove 3/4" hot water requirement for water closet. |
06/04/2009 | RAY MAJUTA | ELECTRICAL-COMMERCIAL | REVIEW | Approved |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
06/09/2009 | DELMA ROBEY | OUT TO CUSTOMER | Completed |
06/09/2009 | SUE REEVES | REJECT SHELF | Completed |