Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL
Permit Number - T09CM01041
Review Name: RESUBMITTAL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
09/18/2009 | RONALD BROWN | ZONING HC | REVIEW | Denied | Reference Building Folder for comments |
09/18/2009 | RICK MYERS | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. At the snack bar three compartment sink, only one compartment may be indirectly wasted if it is a vegetable prep bowl, or a sanitizing bowl. The other two bowls are to be directly connected, like the other three compartment sinks. 2. Response to question asking for floor slope at floor drains, says to refer to the enlarged architectural drawings. Enlarged restroom plans on sheet A-5 do not show the floor drains nor how to slope the floor to them. |
09/18/2009 | RONALD BROWN | BUILDING-COMMERCIAL | REVIEW | Denied | 1. As per Development Services Department standards, all lettering is to be a minimum of 3/32", all capitals. Please correct the following drawings as requested on previous review: CS, CA2, CA3, and CA4. 2. As per previous review comments, Door 152A requires an 18" clearance at strike jamb. 3. Also previously commented, there is a conflict in details 2AG1.1 and 3/M3.1. Please provide a wall section detail clarifying the exhaust requirements of the back of the hood and how and where the stainless steel finish is located and is supported. 4. The revision sheets are a submittal package not included with the full set of documents. A full set of drawings including revised sheets is required for approval stamp. END OF REVIEW. |
09/18/2009 | STEVE SHIELDS | ZONING | REVIEW | Approv-Cond | DSD TRANSMITTAL FROM: Steve Shields Lead Planner PROJECT: SAM's Club Remodel T09CM01041 Site & Building Plan TRANSMITTAL DATE: September 18, 2009 COMMENTS: Please resubmit revised drawings and a response letter, which states how all Zoning Review Section comments regarding the Land Use Code and Development Standards were addressed. The Zoning Review Section conditionally approves the site and building plan for this project, subject to the following: Zoning will stamp and approve the plans once the revised sheets are inserted into to main set of plans and all other reviews are completed and approved. If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956. C:\planning\site\t09cm01041 RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised site plan and additional requested documents. |
09/28/2009 | RAY MAJUTA | ELECTRICAL-COMMERCIAL | REVIEW | Approved | |
09/29/2009 | BIANCA RAMIREZ | ENGINEERING | REVIEW | Approved | . |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
11/23/2009 | CINDY AGUILAR | OUT TO CUSTOMER | Completed |
11/23/2009 | SUE REEVES | REJECT SHELF | Completed |