| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 04/17/2009 | TERRY STEVENS | ZONING | REVIEW | Approved | |
| 04/17/2009 | JOHN WILLIAMS | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Completed | |
| 04/20/2009 | RONALD BROWN | ZONING HC SITE | REVIEW | Denied | 1. SEE BUILDING COMMENTS. |
| 04/22/2009 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Denied | 1. GENERAL: ALL DEFERRED SUBMITTALS MUST BE APPROVED BY THE BUILDING OFFICIAL, JESSIE SANDERS. 2. SHEET A-1; FLOOR PLAN: THE ACCESSIBILITY OF THE WASHER/DRYER AT THE NORTH END OF THE COMPLEX DOES NOT MEET THE ICC/ANSI A117.1-2003 SECTION 1004.10 REQUIREMENT FOR PARALLEL APPROACH. VERIFY AND CHANGE AS REQUIRED. 3. SHEET A-1; WINDOW/GLAZING NOTE 4: ADD REFERENCE IN THIS NOTE TO THE IBC SECTION 1026. 4. SHEET A-1; NOTE #3: ADD REFERENCE IN THIS NOTE TO DETAIL 3 ON SHEET D-3 FOR WALL REINFORCEMENT. 5. STRUCTURAL CALCULATIONS: NEW CALCULATIONS FOR THIS PROJECT MUST INCLUDE VERTICAL AND LATERAL ANALYSIS. PREVIOUSLY APPROVED CALCULATIONS MAY NOT BE USED IN LIEU OF NEW CALCULATIONS. PLEASE PROVIDE FRAMING, FOUNDATION, AND SHEARWALL REFERENCE KEY PLANS FOR THE CALCULATIONS TO AID IN THE PLAN CHECK. 6. GENERAL: EACH NEW PROJECT MUST BE STAMPED, SIGNED, AND DATED BY THE LICENSED ENGINEER AND/OR ARCHITECT OF RECORD. NEW PROJECTS CAN NOT HAVE THE SIGNATURE OR DATE ON PREVIOUSLY APPROVED SHEETS OF A PROJECT ALTERED AND INSERTED INTO THE NEW SET. 7. PROVIDE WRITTEN RESPONSES TO ALL COMMENTS. |
| 05/01/2009 | RICK MYERS | PLUMBING-COMMERCIAL | REVIEW | Denied | see 710.1 2006upc when backwater valve is required. see 904.1 2006upc sewer to be vented. vents located upstream of the bwv shall not be used for meeting cross-sectional area venting requirements. clarify waterpiping material type under slab; p-1 shows type k, p2 shows type l. |
| 05/04/2009 | GERRY KOZIOL | WWM | REVIEW | Denied | NEED CREDIT EVALUATION |
| 05/05/2009 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. If the building energy compliance is not in accordance with ASHRAE 90.1, the duct insulation shall be determined by Section 503.2.7, IECC 2006, as amended by the City of Tucson. Reference: Section 501.2, IECC 2006, as amended by the City of Tucson. 2. The minimum size for a condensate drain is ¾"; no overflow drain is required for a rooftop unit. Reference: Section 307.2, IMC 2006. |
| 05/05/2009 | RMYERS1 | WATER | REVIEW | Passed | |
| 05/08/2009 | RAY MAJUTA | ELECTRICAL-COMMERCIAL | REVIEW | Approved |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 05/13/2009 | DELMA ROBEY | OUT TO CUSTOMER | Completed |
| 05/13/2009 | SUE REEVES | REJECT SHELF | Completed |