Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL TI
Permit Number - T09CM00660
Review Name: COMMERCIAL TI
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 03/26/2009 | BETH GRANT | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Passed | |
| 03/26/2009 | MARTIN BROWN | FIRE | REVIEW | Denied | Please include the following fire sprinkler design criteria to the plans. 1. Flow data (static pressure, residual pressure, GPM) Available from the Fire Department (520) 791-3234 2. The standard to be used in development of sprinkler system. (NFPA 13, NFPA 13R, or NFPA 13D) 3. The hazard classification of the building, including any special hazards. 4. The density required of the water supply. Also, please indicate method of supplying water to sprinkler systems. |
| 03/26/2009 | ERIC NEWCOMB | ADA | REVIEW | Passed | |
| 03/27/2009 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Denied | 1. GENERAL: DWELLING UNITS SHALL BE TYPE B UNITS AS DEFINED IN THE 2006 IBC SECTION 1107.6.2. PROVIDE NOTE ON DRAWINGS. 2. GENERAL: NEW INTERIOR WALLS SHALL BE BRACED TO RESIST LATERAL LOADS REQUIRED IN THE 2006 IBC SECTION 1607.13. PROVIDE DETAIL(S) INDICATING THE CONNECTION OF THE TOP OF THE INTERIOR WALL TO THE ROOF STRUCTURE, AND OF THE BOTTOM OF THE INTERIOR WALL TO THE FLOOR. INCLUDE IN THESE DETAILS CONNECTION SIZE, SPACING, AND QUANTITY. |
| 03/30/2009 | ERIC NEWCOMB | ZONING HC SITE | REVIEW | Denied | 1. SEE BUILDING COMMENTS. |
| 03/31/2009 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. Clarify the differences between the mechanical specifications and the scheduled split system heat pumps; the specifications appear to call for a packaged heat pump instead of a split system. Reference: Section 106.3.1, IMC 2006. 2. Provide manufacturer's equipment data along with the mechanical (e.g. heating and cooling capacity) and electrical operating information for the new split system heat pumps. Reference: Section 301.6, IMC 2006. 3. Show how the fan coils are being connected to the building structure and provide calculations to show that the building structure is not being adversely affected. Reference: Section 302.1, IMC 2006. 4. Show that the heating and cooling capacities of the new heat pump systems can meet the calculated heating load. Reference: Section 309.1, IMC 2006. 5. For the purposes of the 2006 International Energy Conservation Code, R-2 buildings shall comply with the residential energy efficiency requirements (chapter 4). Reference: Section 202, IECC 2006. 6. Specify the minimum resistance (R-value) of the duct insulation to be used on this project. Reference: Section 403.2, IECC 2006. 7. Specify the minimum resistance (R-value) of the foam insulation to be installed in the roof/ceiling assembly (sheet A-8.1). Reference: Section 402.12, IECC 2006. |
| 03/31/2009 | ROBERT SHERRY | WATER | REVIEW | Denied | Provide site drawing showing the size and route of the building water supply along with the location and size of both the water meter and the reduced pressure backflow preventer assembly. Reference: Section 103.2.3, UPC 2006 |
| 04/01/2009 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Provide the water pressure calculations that were used to determine the water pressure available at the building entrance. Reference: Sections 103.2.3, UPC 2006. 2. Provide a site drawing showing the size, route, and slope of the extension of the building sewer to the public sewer connection. Reference: Section 103.2.3, UPC 2006. 3. Provide manufacturer's equipment data (e.g. model number, flow rate, and temperature rise) along with the electrical operating information for the tankless water heaters. Reference: Section 301.6, IMC 2006. 4. Provide fixture descriptions for all plumbing fixtures. All plumbing fixtures and fittings shall be listed or labeled by a nationally-recognized, accredited conformity assessment company (e.g. UL, ETL, UPC, etc). Reference: Sections 301.1.1 and 401.1, UPC 2006. 5. Substitution of alternate piping materials (e.g. PEX instead of copper piping) will require a revision of the water pipe sizing calculations to match the revised piping materials. Reference: Sections 103.2.3 and 610.0, UPC 2006. |
| 04/01/2009 | DAVID RIVERA | ZONING | REVIEW | Approved | |
| 04/01/2009 | RAY MAJUTA | ELECTRICAL-COMMERCIAL | REVIEW | Approved | |
| 04/02/2009 | GERRY KOZIOL | WWM | REVIEW | Denied | need 5th floor credit evaluation |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 04/14/2009 | CINDY AGUILAR | OUT TO CUSTOMER | Completed |