Permit Number: T09CM00570
Parcel: 14016003F

Review Status: Completed

Review Details: COMMERCIAL-BLDG/FIRE/ZONING/ENG

Permit Number - T09CM00570
Review Name: COMMERCIAL-BLDG/FIRE/ZONING/ENG
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
03/12/2009 JOHN WILLIAMS COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Passed
03/13/2009 MARTIN BROWN FIRE REVIEW Approved
03/17/2009 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Denied 1. ALL DEFERRED SUBMITTALS MUST BE APPROVED BY THE BUILDING OFFICIAL, JESSIE SANDERS.
2. INCLUDE CODE ANALYSIS DATA ON THE DRAWINGS PER IBC SECTION 106.1.1. INFORMATION SHOULD INCLUDE OCCUPANCY GROUP, OCCUPANCY LOAD, EXIT REQUIREMENTS, ACCESSIBILITY REQUIREMENTS, PLUMBING REQUIREMENTS, HOW THE NEW OCCUPANCY LOAD AFFECTS EXISTING CONDITIONS, ETC.
3. SHEET A1; FOUNDATION PLAN: THE ACCESSIBLE TURNING CIRCLE SHOWN ON THE PLAN INDICATES THAT THE RESTROOMS ARE ACCESSIBLE. WHY ARE THESE INDICATED ON THIS PROJECT?
4. SHEET A1; SHEAR WALL/HOLDOWN SCHEDULES: ENLARGE THE PRINT TO A MINIMUM OF 3/32" FOR CLARITY.
5. SHEET A3; ROOF FRAMING PLAN: PROVIDE DETAILS FOR THE NEW ROOF TRUSSES OVER THE EXISTING ROOF FRAMING. INDICATE NEW FRAMING AND CONNECTIONS AT THE OVERFRAMING.
6. SHEET A3; ROOF FRAMING PLAN: PROVIDE A DETAIL TO BRACE AND SUPPORT THE TOP OF THE NEW INTERIOR, NON BEARING WALLS TO RESIST LATERAL FORCES REQUIRED BY IBC SECTION 1607.13.
7. SHEET A3; ROOF FRAMING PLAN: ADD LINTEL DESIGNATION L-1 TO NEW OPENING IN EXISTING WALL.
8. SHEET MP1; MECHANICAL FLOOR PLAN: PROVIDE DESIGN AND DETAILS OF THE WALL AND WALL FOUNDATION AT THE CONDENSING UNITS.
03/25/2009 RAY MAJUTA ELECTRICAL-COMMERCIAL REVIEW Approved
03/26/2009 RSHERRY1 WWM REVIEW Passed No new plumbing fixtures.
03/26/2009 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Denied 1. Provide energy code compliance calculations for the building envelope. Provide sufficient detail on the drawings to evaluate the energy compliance of the building envelope. The information shall, as a minimum, include U-factors of the envelope systems and fenestration components, along with the R-values of the insulation. Reference: Sections 101.4 and 104.2, International Energy Conservation Code 2006.
2. Show how the fan coil is being connected to the building structure and provide calculations to show that the building structure is not being adversely affected. Reference: Section 302.1, IMC 2006.
3. Show how adequate access is being provided for the equipment located in the attic space. Reference:: Section 306.3, IMC 2006.
4. Clarify the termination points for the relocated and the new condensate drains. Condensate drains that terminate to the outside shall not cause any surface runoff. (Note that keynote #9 does not seem to appear on the mechanical floor plan.) Reference: Section 307.2.1, IMC 2006, as amended by the City of Tucson.
03/26/2009 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Approved
03/31/2009 TERRY STEVENS ZONING REVIEW Denied 03/31/2009

Development Services Department
Zoning Review Section

Terry Stevens
Lead Planner

Comments:

1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed.

2. Zoning could not verify that the building plan was in compliance with the approved development plan. Please submit two copies of the approved and stamped development, landscape, and NPPO plans with the next building plan submittal.

3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved site/development plan. Additional comments may be forthcoming.
04/09/2009 PAUL MACHADO ENGINEERING REVIEW Approved

Final Status

Task End Date Reviewer's Name Type of Review Description
04/17/2009 GERARDO BONILLA OUT TO CUSTOMER Completed
04/17/2009 SUE REEVES REJECT SHELF Completed