Permit Number: T09CM00312
Parcel: 125130650

Address:
3148 E 2ND ST

Review Status: Completed

Review Details: RESUBMITTAL - SITE

Permit Number - T09CM00312
Review Name: RESUBMITTAL - SITE
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
04/08/2009 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Approved
04/13/2009 TERRY STEVENS ZONING REVIEW Denied DSD TRANSMITTAL

FROM: Terry Stevens
Lead Planner

PROJECT: T09CM00312
3148 E. 2nd Street
Site Plan

TRANSMITTAL DATE: 4/13/09

COMMENTS: Please resubmit revised drawings along with redlines and a response letter, which states how all Zoning Review Section comments regarding the Land Use Code and Development Standards were addressed.

1. DS 2-02.2.1.2 A tax parcel combination for all four parcels must be completed prior to approval of the site plan. Provide documentation indicating approval of the tax parcel combination. The site plan will be approved conditionally once this is the only remaining comment. A hold will be placed on any building permits being issued until the lot combo has been completed.

2. DS 2-05.2.2.B.6 If the DSMR (D09-08)is approved for this project, please add the DSMR number, date of approval, what the DSMR is applied and approved for, and any conditions of approval on the site plan as a general note on sheet C-1. The indicated date of approval is incorrect as the DSMR has not been approved as of this review.

3. DS 2-02.2.1.7 In the zoning code check portion of sheet C-1, change the minimum setbacks from rear and side yard to the south property line and west property line.

4. DS 2-02.2.1.20 If applicable, all easements of record and proposed easements must be shown on the plan together with recording docket and page.

Per letter from Damian Fellows and a search of aerial photos (power poles and overhead electrical lines) the 20' wide parcel located along the south side of this project appears to be a utility easement. Provide recording docket and page information on the site plan and clearly indicate the location and use of the easement on the site plan. It appears that building unit #1 will encroach into this easement. Provide written documentation, from any and all utility companies which may have a claim to this easement, clearly indicating their approval for construction within this easement.

5. Depending on changes made to this site plan and responses to the above comments additional comments may be forth coming.


If you have any questions about this transmittal, please call Terry Stevens, (520) 837-4961

C:\planning\cdrc\DSD\T09CM00312-2.doc

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised site plan and additional requested documents
04/17/2009 BIANCA RAMIREZ ENGINEERING REVIEW Denied DATE: April 17, 2009
SUBJECT: Site Plan
TO: Wally Gasser
LOCATION: 3148 E 2nd Street, T14S, R14E, Section 9, Ward 6
REVIEWERS: Bianca Ramirez, CFM
ACTIVITY: T09CM00312 (Second Review)


RESUBMITTAL REQUIRED: Site Plan

SUMMARY: Engineering Division of Development Services Department has received and reviewed the proposed site plan for the above referenced property. Engineering Division does not recommend approval of the site plan at this time. Please address the following review comments prior to the next submittal.

Please include a response letter to the comments along with the corrected copies of the site plan.
Site Plan:

1. Complied
2. Please verify that all text is a minimum of 0.12 fonts. Verify that text for location map is meeting minimum text requirement.
3. Please provide property description per D.S. 2-02.2.1.2. Property description does not match for address provided. Acknowledge that lot combo is in progress.
4. Complied
5. Complied
6. Complied
7. Complied
8. Label existing and future sight visibility triangles per D.S. 2-02.2.1.10. Provide proof from the transportation department that there is on street parking. An email to Bianca Ramirez @ bianca.ramirez@tucsonaz.gov will suffice. Verify that all SVT's are labeled correctly.
9. Complied
10. DS Sec.2-02.2.1.A.11 & DS Sec.3-01.3.2.C: label curb radii concrete curbs at the driveway entrance along Anderson Blvd. Verify that curb returns are acceptable at this location.
11. Complied
12. Complied
13. Acknowledged
14. Complied
15. Complied
16. Complied
17. DS Sec. 2-05.2.4.H.2: Provide the right-of-way (ROW) recordation information for Anderson Blvd and 2nd Street. Book and Page presented on response letter. Please add to site plan.
18. Complied
19. Complied
20. Complied
21. Complied
22. Show Site plan activity number in the lower right hand corner of each sheet per D.S. 2-02.2.1.29. Please remove date for DSMR if it has yet to be approved. See Zoning comments regarding DSMR.
23. See refuse contained detail previously enclosed and ensure that all components are called out within detail in accordance with the detail. Depict concrete approach slab.
24. Complied
25. A permit or a private improvement agreement will be necessary for any work performed within the Right-of-way. Contact Permits and Codes at (520) 791-5100 for permit information.
26. Complied
27. Full describe called our reference point on site plan at the intersection of 2nd Street and Anderson Blvd.
28. Additional comments may be forthcoming.

If you have any questions, I can be reached at 837-4928 or Bianca.Ramirez@tucsonaz.gov

Bianca C. Ramirez
Engineering Associate
City of Tucson/Development Services Department
201 N. Stone Avenue
P.O. Box 27210
Tucson, Arizona 85726-7210
(520) 837-4928 office
(520) 879-8010 fax
04/20/2009 CAGUILA1 NPPO REVIEW Needs Review
04/20/2009 CAGUILA1 LANDSCAPE REVIEW Needs Review