Permit Review Detail
Review Status: Completed
Review Details: POST 3RD PARTY REVIEW
Permit Number - T09CM00299
Review Name: POST 3RD PARTY REVIEW
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 02/12/2009 | JOHN WILLIAMS | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Passed | |
| 02/12/2009 | ROBERT SHERRY | WATER | REVIEW | Approved | |
| 02/12/2009 | DAVE MANN | FIRE | REVIEW | Denied | Please include the following design criteria to the plans. 1. Flow data (static pressure, residual pressure, GPM) Available from the Fire Department (520) 791-3234 2. The standard to be used in development of sprinkler system. (NFPA 13, NFPA 13R, or NFPA 13D) 3. The hazard classification of the building, including any special hazards. 4. The density required of the water supply. Please indicate existing fire hydrant location(s), with dimensions to buildings and/or property lines. Refer to City of Tucson amendments to the 2006 International Fire Code (section 508) for spacing and location requirements. |
| 02/12/2009 | RONALD BROWN | ADA | REVIEW | Passed | NOT A COT PROJECT |
| 02/12/2009 | BIANCA RAMIREZ | ENGINEERING | REVIEW | Approved | |
| 02/13/2009 | GERRY KOZIOL | WWM | REVIEW | Approved | |
| 02/19/2009 | RONALD BROWN | ZONING HC SITE | REVIEW | Passed | THIRD PARTY ACCESSIBLE REVIEW REFERENCE WILDAN COMMENTS |
| 02/20/2009 | TERRY STEVENS | ZONING | REVIEW | Denied | 02/23/2009 Development Services Department Zoning Review Section Terry Stevens Lead Planner Comments: 1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan as submitted. Per Development plan D07-0017 and sheet A1.2 of the building plans, there is a 20' space between building 1-N and building 1-S. The building 1-N per the building plans is 100' in length. Per the DP the maximum length of the building is 80'. Revise the building plan to comply or a revised development plan will be required to accommodate the increase in the size of the building,. |
| 02/27/2009 | JEFF DRUMM | LANDFILL | REVIEW | Approved |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 03/02/2009 | GERARDO BONILLA | OUT TO CUSTOMER | Completed |
| 03/02/2009 | SUE REEVES | REJECT SHELF | Completed |