Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL
Permit Number - T09CM00283
Review Name: RESUBMITTAL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
04/02/2009 | STEVE SHIELDS | ZONING | REVIEW | Approved | |
04/02/2009 | MARTIN BROWN | FIRE | REVIEW | Approved | |
04/03/2009 | RONALD BROWN | BUILDING-COMMERCIAL | REVIEW | Denied | A GENERAL NOTE: NONE OF THE PREVIOUS BUILDING COMMENTS WERE RECOGNIZED AND ACTED UPON. A COPY OF THOSE HAVE BEEN ADDED BELOW FOR COMPLIANCE. PLEASE REVIEW THESE COMMENTS AND PROVIDE RESPONSES AND DRAWING CORRECTIONS ACCORDINGLY. 1. SHEET A-1; MEN'S RESTROOM: MAKE SURE THE NEW LOCKER ROOM AREA IS ACCESSIBLE (5'-0" TURNING SPACE). 2. SHEET A-1; WOMEN'S RESTROOM: PROVIDE ACCESSIBLE SHOWER (ROLL-IN OR TRANSFER-TYPE) PER ICC/ANSI A117.1-2003 SECTION 608. INDICATE GRAB BARS, SEAT, AND CLEARANCES AS REQUIRED. 3. SHEET A-1; DOOR SWINGS: CHECK DOOR SWINGS, APPROACHES, AND CLEARANCES FOR SWINGING DOORS PER 2003 ANSI SECTION 404 (DOORS 113 AND 114). 4. SHEET A-2; DIMENSIONED RESTROOM PLAN: THE NEW WOMEN'S RESTROOM IS REQUIRED TO BE ACCESSIBLE PER THE 2006 IBC SECTION 1109.2 AND/OR SECTION 3409. PROVIDE TURNING SPACE REQUIREMENTS PER 2003 ANSI SECTION 304, CLEAR FLOOR SPACE PER SECTION 305, KNEE AND TOE CLEARANCE PER SECTION 306, AND PLUMBING ELEMENTS PER CHAPTER 6. INDICATE THESE REQUIREMENTS ON THE DRAWINGS. 5. SHEET A-5; ROOM FINISH SCHEDULE: WOMEN'S RESTROOM WALLS SHALL MEET THE REQUIREMENTS OF THE 2006 IBC SECTION 1210.2. 6. SHEET A-7: ACCESSIBLE COUNTERS AND CABINETS SHALL HAVE TOP ELEVATIONS 34" ABOVE THE FINISHED FLOOR PER 2003 ANSI CHAPTER 9. 7. SHEET A-7; DETAIL 13: PROVIDE CONNECTIONS OF THE INTERIOR PARTITIONS AT THE TOP AND BOTTOM OF THE WALL TO RESIST LOADS SPECIFIED IN THE 2006 IBC SECTION 1607.13. INCLUDE CONNECTOR SIZE AND QUANTITY AT EACH LOCATION. 8. GENERAL: PROVIDE THE REQUIRED PLUMBING FIXTURES PER THE 2006 IBC CHAPTER 29, OR AN ANALYSIS OF EXISTING FIXTURES FOR THE ENTIRE BUILDING, INCLUDING THE ADDITION OF THE NEW SQUARE FOOTAGE. 9. GENERAL: PROVIDE DIMENSIONED, LARGE-SCALE PLANS AND WALL ELEVATIONS FOR ACCESSIBLE AREAS PER THE 2006 IBC AND THE 2003 ANSI. 10. GENERAL: ENSURE THAT THE BUTLER BUILDING DRAWINGS ARE ATTACHED TO THE FULL SIZE DRAWING SET. |
04/03/2009 | RONALD BROWN | ZONING HC SITE | REVIEW | Denied | REFERENCE BUILDING FOLDER COMMENTS |
04/22/2009 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Comment not addressed. Clarify the roof drainage calculations and plans; the roof areas used for calculating the downspout sizes do not appear to match the drawings. Reference: Section 1106.0, UPC 2006. 2. Comment not addressed. Revise the north arrow on the plumbing floor plans to match the orientation of the building. Reference: Section 103.2.3, UPC 2006. 3. Comment not addressed. Provide upper terminal cleanouts on horizontal drainage pipes exceeding 5 feet in length (P-2). Horizontal drain lines serving sinks require cleanouts regardless of length (P-3). Reference: Section 707.4, UPC 2006. 4. Comment not addressed. Provide the size of the existing CW and HW lines to which the new CW and HW piping is being connected (Keynotes 5, 6, 7, and 11, P-1). Reference: Section 103.2.3, UPC 2006. 5. Comment not addressed. Provide a floor drain in the women's restroom. Reference: Section 411.2, UPC 2006. |
04/22/2009 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. Comment not addressed. Provide information on the sequence of operation for the relocated restroom exhaust fan in the women's restroom to show that recirculation of the air from the restroom will not occur. Reference: Section 403.2.1, IMC 2006. 2. Comment not addressed. Provide structural calculations to verify that the existing roof is capable of supporting the additional dead load due to the installation of the condensing units. Reference: Section 302.1, IMC 2006. 3. Comment not addressed. Show how the fan coils are being connected to the building structure and provide calculations to show that the building structure is not being adversely affected. Reference: Section 302.1, IMC 2006. 4. Comment not addressed. Clarify the orientation of the cleanouts for the condensate drain piping. Reference: Section 106.3.1, IMC 2006. 5. Comment not addressed. Provide energy code compliance calculations for the building addition. Provide sufficient detail on the drawings to evaluate the energy compliance of the building envelope. The information shall, as a minimum, include U-factors of the envelope systems and fenestration components, along with the R-values of the insulation. Reference: Section 101.4, International Energy Conservation Code 2006. 6. Comment not addressed. If the building energy compliance is not in accordance with ASHRAE 90.1, the duct insulation shall be determined by Section 503.2.7, IECC 2006, as amended by the City of Tucson. Reference: Section 501.2, IECC 2006, as amended by the City of Tucson. |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
04/24/2009 | SUE REEVES | APPROVAL SHELF | Completed |
04/24/2009 | DELMA ROBEY | OUT TO CUSTOMER | Completed |