Permit Review Detail
Review Status: Completed
Review Details: GRADING
Permit Number - T09BU01106
Review Name: GRADING
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
08/12/2009 | ANDREW CONNOR | NPPO | REVIEW | Approv-Cond | |
08/14/2009 | STEVE SHIELDS | ZONING | REVIEW | Denied | DSD TRANSMITTAL FROM: Steve Shields Lead Planner PROJECT: Cherry Avenue Center T09BU01106 Grading Plan (1st Review) TRANSMITTAL DATE: August 14, 2009 1. The grading plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed. 2. Zoning could not verify that the grading plan was in compliance with the approved site plan. Please submit two copies of the approved and stamped site, landscape, and NPPO plans with the next grading plan submittal. 3. Zoning will re-review the grading plan on the next submittal to insure compliance with the approved and stamped site plan. Additional comments may be forthcoming. If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956 C:\planning\grading\t09bu01140 RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Approved site plans and additional requested documents |
09/04/2009 | PAUL MACHADO | ENGINEERING | REVIEW | Denied | To: John Hucko 3025 W. Ina Road Tucson, Arizona 85741 Subject: Cherry Avenue Center, 5085 S. Cherry Ave. Grading plan T09BU01106 (First Review) T15S, R14E, Section 06 RESUBMITTAL REQUIRED: Grading Plan and Drainage Statement. The Grading Plan (GP) and Drainage Statement (DS) cannot be approved as submitted. Please address the following review comments prior to the next submittal. Grading Plan: 1. Please include a response letter to the comments along with the corrected copies of the GP. 2. The grading plan cannot be approved prior to the Site Plan. 3. Add the following notes to the grading plan: " "The approved Grading Plan is the only acceptable construction plan onsite. The Contractor may not use any other plans, such as the approved the Site Plan, Tentative Plat and/or Development Plan, for construction purposes. The Contractor may ask the Development Services Inspector to consult with the other approved plans for additional information or details that might not be included on the approved grading plan but needed for completion of work." " "The contractor shall remove the fine materials from the bottom of the detention/retention basin and scarify the basin bottom once the construction activities are completed in order to remove any fine material build up caused by construction and to restore soil percolation." " "Any engineering work to be done below grade (i.e. toe-downs, cutoff walls, drainage pipes/structures, etc.) shall not be back filled until Development Services Inspector inspects the work and approves it." 4. Add note: "Depress all landscaped areas a maximum of 6" for water harvesting" 5. List administrative address/site address on plans. 6. List the Site Plan (T09CM02029) and the Grading plan (T09BU01106) number on each sheet. 7. A permit or a private improvement agreement will be necessary for any work performed within the Right-of-way. Contact Permits and Codes at (520) 791-5100 for permit information. 8. Flow arrows, grades and flow rates within and adjacent to site to show drainage scheme. 9. Call out peak discharges entering and exiting the site. Drainage Statement: 1. Please include a response letter to the comments along with the corrected copies of the DS. 2. A Drainage Statement is a brief description of drainage conditions applicable for a site which are not affected by 100 year flows of 100 cfs, of more……per S.M.D.D.F.M., chap. II, 2.1.2. The DS must be submitted along with the site plan and accepted with the approval of the grading plan. 3. The content and format of the Drainage Statement should follow S.M.D.D.F.M., chap. II, 2.2. 4. Show the project address or administration address on the cover sheet of the DS. If you have any questions, I can be reached at 837-4932 or Paul.Machado@tucsonaz.gov Paul P. Machado Senior Engineering Associate City of Tucson/Development Services Department 201 N. Stone Avenue P.O. Box 27210 Tucson, Arizona 85726-7210 (520) 837-4932 office (520) 879-8010 fax C:\5085 S. Cherry Ave_Grad |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
09/14/2009 | CPIERCE1 | OUT TO CUSTOMER | Completed |
09/14/2009 | SUE REEVES | REJECT SHELF | Completed |