Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Plan Review Detail
Review Status: Completed
Review Details: PIA RESUBMITTAL
Plan Number - T08PI00005
Review Name: PIA RESUBMITTAL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
08/14/2008 | SMONTIE1 | UTILITY CLEARANCES | COT STREETS DIVISION | Completed | Please submit Utility Clearance Letters for: Kinder Morgan Energy, & El Paso Natural Gas. If not applicable we still need the receipt showing N/A. |
08/14/2008 | SMONTIE1 | UTILITY CLEARANCES | COT WATER NEW DEVELOPMENT | Completed | Please submit Utility Clearance Letters for: Kinder Morgan Energy, & El Paso Natural Gas. If not applicable we still need the receipt showing N/A. |
08/14/2008 | SMONTIE1 | UTILITY CLEARANCES | PC WASTEWATER MGMT | Completed | Please submit Utility Clearance Letters for: Kinder Morgan Energy, & El Paso Natural Gas. If not applicable we still need the receipt showing N/A. |
08/14/2008 | SMONTIE1 | UTILITY CLEARANCES | QUEST COMMUNICATION | Completed | Please submit Utility Clearance Letters for: Kinder Morgan Energy, & El Paso Natural Gas. If not applicable we still need the receipt showing N/A. |
08/14/2008 | SMONTIE1 | UTILITY CLEARANCES | TUCSON ELECTRIC POWER CO | Completed | Please submit Utility Clearance Letters for: Kinder Morgan Energy, & El Paso Natural Gas. If not applicable we still need the receipt showing N/A. |
08/14/2008 | SMONTIE1 | UTILITY CLEARANCES | COX COMMUNICATION | Completed | Please submit Utility Clearance Letters for: Kinder Morgan Energy, & El Paso Natural Gas. If not applicable we still need the receipt showing N/A. |
08/14/2008 | SMONTIE1 | UTILITY CLEARANCES | SOUTHWEST GAS CORP | Completed | Please submit Utility Clearance Letters for: Kinder Morgan Energy, & El Paso Natural Gas. If not applicable we still need the receipt showing N/A. |
08/14/2008 | SMONTIE1 | UTILITY CLEARANCES | EL PASO NATURAL GAS | Denied | Please submit Utility Clearance Letters for: Kinder Morgan Energy, & El Paso Natural Gas. If not applicable we still need the receipt showing N/A. |
08/14/2008 | SMONTIE1 | UTILITY CLEARANCES | KINDER MORGAN ENERGY | Denied | Please submit Utility Clearance Letters for: Kinder Morgan Energy, & El Paso Natural Gas. If not applicable we still need the receipt showing N/A. |
08/19/2008 | GARY WITTWER | DOT LANDSCAPE | REVIEW | Approved | |
09/04/2008 | Blanca Espino | DOT ENGINEERING | REVIEW | Denied | PIA Plan 1. Please include a detail letter of explanation with the next submittal indicating where and how revisions were made. Single word responses are unacceptable. Include plans/redlines from previous plan submittal. 2. This review was incomplete since copies of the drainage or Geotechnical reports were not included in submittal. Submit an approved copy of the Drainage Report & Geotechnical Report. 3. Follow the City of Tucson, Engineering Division Active Practice Guidelines for Drafting Standards for the preparation of Project Plans, Office Procedure No. 8-1552-002. (see attached). 4. Sheet 1, Indicate the DSD activity number of the two DSMR's above title block. See redlines. 5. Recording information of Maps and Plats, Book and Page must be noted on cover sheet of subdivision street improvement plans. Plat must be recorded before submittal of mylars for final review and approval. See redlines. 6. Sheet 2, Paving Note #17; indicate the report's name, firm name & project number. 7. Paving Note #19; indicate the floodplain use permit activity number issued by DSD. 8. Indicate the DSMR approved conditions following the Paving Notes on Sheet 2. 9. Overview map, the reference numbers shown for the sheet pages are incorrect. 10. Legend, indicate all symbols shown in PC/COT Std. Dtl. 100 that are to be used on plan. All line work must reference Std. Dtl. 100. All existing lines are to be represented with a dashed line. Also indicate the Feature abbreviations; BCR, ECR, PT, etc. along with Stationing, Offset & Elevations. Correct all points. 11. Previous comment: A Floodplain Use Permit is required for work along and or within the Palm Tree Drive Wash. Application can be picked up and submitted to Development Services Engineering. Explain how it has been "Noted". 12. Sheet 3, Plan view; delineate the 1-foot saw-cut area(s). Indicate the Beginning and Ending along with the Stationing, Offset and elevations. These markings should be spaced every 50 feet. See redlines. Show symbol in Legend of Sheet 2. 13. Profile, 22nd Street, Sta. 41+33.10; indicate elevation. Identify line symbol. See redlines. 14. Detail Section X-X; existing pavement thickness and surface treatment shall be matched. Use a light grey colored dashed line for existing line work. 15. Detail Section Y-Y; use a light grey colored dashed line for existing line work. 16. Sheet 4, place this sheet at the end of plan set. Change sheet page to read 8 of 8. 17. Sheet 5; indicate drainage arrows for left plan view. 18. Left view, Check curve data. It conflicts with Tentative Plat. Face of curb line must be parallel with property line. Reflect changes in Curve Table. Correct and revise. 19. Lot #101 is not shown on either left or right plan views. Correct. 20. Sheet 5, the Vertical curve between Sta.10+78.79 & Sta.11+63.90 is to be designed to meet minimum stopping sight distance. The proposed design does not meet Development Standard 3-01.4.5.B. Provide 2% maximum cross slope for pedestrian access route. Correct and revise. 21. Ramps located at Curve C3, C8 and the two handicap ramps located at the "T" turnaround show all to be different. A dimensioned detail for each type of curb access ramp to be built as part of the project must be shown. 22. Lettering size for Paving Improvement plans is equal to or greater than 1/8 inch in height (125 point). Correct text as noted. See redlines. 23. Sheet 6; Indicate a dimensioned detail of "T" turnaround. Indicate curve data in Curve table. 24. All Easements, dedications, right-of-way should be depicted in plan view and labeled with recordation information (docket/page or plat book/page). 25. A private drainage access easement will be required for the drainage structural being built in a public drainageway. 26. Curve C12 is to have a Radius of 42' from back of wedge curb. Correct leader to point to back of wedge curb. 27. Detail Section X-X on Sheet 6 should be renamed due to an existing detail on Sheet 3 with the same name. Graphically indicate callout on plan view. 28. Detail Section X-X will need to be Keyed into bank. 29. Ramps opposite of one another must line up. All curb access ramps should have the 6-inch curb at back of ramp. 30. Provide 2% maximum cross slope for pedestrian access route. 31. Sheet 7; the Cul-de-sac design must meet D.S. 3-01.10.Figure 21 design. Correct. 32. Curve C12 is to have a 42-foot radius from back of wedge curb. See Figure 21 of D.S. 3-01.10 Indicate the curve data for curve in lot 50. See redlines for location. 33. Sheets 3 to 7; Provide survey monuments on street monument line per D.S. 2-03.6.5.C.6 Provide monument line data. Indicate the survey monument symbol in legend of Sheet 2. 34. Call-out all curb transitions. Indicate Feature abbreviation, Stationing, Offset & Elevations. 35. All Plan view Stationing must be aligned with Profile stationing. Correct all sheets. 36. Check curve data. It conflicts with Tentative Plat. Face of curb line must be parallel with property line. Reflect changes in Curve Table. Correct and revise. 37. Indicate the Street names under all plan views. Correct all sheets. 38. Indicate the drainage flow amounts, Q's, through each sidewalk scupper location. Correct all sheets. 39. Key Note #7; indicate number of cells (typical). 40. Lettering size for Paving Improvement plans is equal to or greater than 1/8 inch in height (125 point). Correct all sheets. 41. Use a different pen weight for grid lines. It is difficult to differentiate existing & proposed line work with grid lines. Correct all sheets. 42. Indicate the street centerline. Correct all sheets. 43. Profile views; label all existing and proposed line work. See redlines. Correct all sheets. 44. See redlines for additional corrections. 45. Indicate the outline of the existing "T" turnaround and removal. Once changes, modifications, and or corrections are made to the PIA plan resubmitted and reviewed, further comment may result. If you have any questions, I can be reached at 837-6634 or Blanca.Espino@tucsonaz.gov |
09/12/2008 | LANCE PETERSON | DOT STREET MAINTENANCE | REVIEW | Denied | We have reviewed this plan and have the following comments: 1. Sheet 6 - Who will be responcible for the maintenance of the pedestrian walkway? 2. Sheet 6 - What is the proposed thickness of the rip rap pad in the Palm Tree Drive Wash? 3. Sheet 6 - The concrete bank protection appears to be 6 inches thick. Will there be welded wire mesh installed in the bank protection? 4. Sheet 6 - Is there access available for City crews to maintain the wash? 5. Any driveways installed on 22nd Street will need to be sleeved and irrigation replaced. Also, repair any irrigation that is damaged and replace any landscaping that is removed or damaged. No further comments |
09/18/2008 | JOSE ORTIZ | DOT TRAFFIC | REVIEW | Denied | September 18, 2008 ACTIVITY NUMBER: T08PI00005 PROJECT NAME: Barrio Arroyo PROJECT ADDRESS: 8525 E 22nd St PROJECT REVIEWER: Jose E. Ortiz PE, Traffic Engineer Resubmittal Required: Traffic Engineering does not recommend approval of the PIA Plan; therefore a revised PIA Plan is required for re-submittal. Additional comments will be required due to the modification to the eastern access point. The following items must be revised or added to the plan. 1. Include a response letter with the next submittal that states how all comments have been addressed. 2. See redlines on the submitted drawings and address the additional redline comments. During the next submittal please re-submit the roll of redlines for back checking purposes. If you have any questions, I can be reached at 791-4259 x76730 or Jose.Ortiz@tucsonaz.gov |
09/19/2008 | SMONTIE1 | PIA COORDINATOR | CUSTOMER CALLED; PLANS @ AMBASSADOR | Completed | |
09/19/2008 | SMONTIE1 | PIA COORDINATOR | OUT TO CUSTOMER | Completed |