Plan Review Detail
Review Status: Completed
Review Details: PIA SUBMITTAL
Plan Number - T08PI00003
Review Name: PIA SUBMITTAL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
01/18/2008 | SMONTIE1 | UTILITY CLEARANCES | COT STREETS DIVISION | Denied | PLEASE SUBMIT UTILITY CLEARANCE LETTERS |
01/18/2008 | SMONTIE1 | UTILITY CLEARANCES | COT WATER NEW DEVELOPMENT | Denied | PLEASE SUBMIT UTILITY CLEARANCE LETTERS |
01/18/2008 | SMONTIE1 | UTILITY CLEARANCES | PC WASTEWATER MGMT | Denied | PLEASE SUBMIT UTILITY CLEARANCE LETTERS |
01/18/2008 | SMONTIE1 | UTILITY CLEARANCES | QUEST COMMUNICATION | Denied | PLEASE SUBMIT UTILITY CLEARANCE LETTERS |
01/18/2008 | SMONTIE1 | UTILITY CLEARANCES | TUCSON ELECTRIC POWER CO | Denied | PLEASE SUBMIT UTILITY CLEARANCE LETTERS |
01/18/2008 | SMONTIE1 | UTILITY CLEARANCES | COX COMMUNICATION | Denied | PLEASE SUBMIT UTILITY CLEARANCE LETTERS |
01/18/2008 | SMONTIE1 | UTILITY CLEARANCES | SOUTHWEST GAS CORP | Denied | PLEASE SUBMIT UTILITY CLEARANCE LETTERS |
01/18/2008 | SMONTIE1 | UTILITY CLEARANCES | EL PASO NATURAL GAS | Denied | PLEASE SUBMIT UTILITY CLEARANCE LETTERS |
01/18/2008 | SMONTIE1 | UTILITY CLEARANCES | KINDER MORGAN ENERGY | Denied | PLEASE SUBMIT UTILITY CLEARANCE LETTERS |
02/07/2008 | LANCE PETERSON | DOT STREET MAINTENANCE | REVIEW | Denied | We have reviewed this plan and have the following comments: 1. Please provide a Streets and Traffic Maintenance signature block. 2. Sheet 2 - Please provide station and offsets for the start and end of the concrete header. 3. Sheet 3 - It appears that some of the improvements are on private property. Who will be responcible for the maintenance of these improvements? 4. Sheet 3 - Note 12 - This note states to end the curb and sidewalk but it does not provide the station and offsets. 5. Is the drainage shown publis or private? The access to the drainage appears to be outside of the right of way. 6. Will there be any landscaping installed with this project? If so, please provide the landscape plan to Paul Rosenboom at 4004 S. Park Ave Bld #2 for review. 7. All work in the right of way needs to be coordinated with Paul Rosenboom at 791-5279 ext 234 to prevent damage to existing irrigation and landscaping. No further comments. |
02/08/2008 | GARY WITTWER | DOT LANDSCAPE | REVIEW | Denied | Please address the Native Plant Preservation Ordinance. |
02/11/2008 | RICHARD LEIGH | DOT ENGINEERING | REVIEW | Denied | January 28, 2008 SUBJECT: Sun Tran BSMF-Phase 2, Smoot Drive, PIA T08PI0003 PROJECT REVIEWER: Richard Leigh, DOT, Permits and Codes Section RESUBMITTAL REQUIRED: Permits and Codes Section has reviewed the PIA Plan and does not recommend approval of the PIA Plan at this time. The following comments need to be addressed in the next submittal. 1. Use current PIA title block. See attached. 2. Include the plan number "I-2008-004" in title block of each sheet. 3. Include Development Services Department PIA activity number (T0800003) on cover sheet. 4. Remove signature line for COT Traffic Engineer. 5. Relocate gate post for the channel maintenance access ramp outside of the public right-of-way. 6. The cross slope for pedestrian crosswalk area across Smoot Drive must not exceed 2%. 7. Sheet 5: Remove gate details or crossout and indicate that they are not part of the P.I.A. Refer to redline plans for additional comments and comment details. If you have any questions, I can be reached at 837-6647 or Richard.Leigh@tucsoz.gov |
02/25/2008 | SMONTIE1 | PIA COORDINATOR | CUSTOMER CALLED | Completed | |
02/25/2008 | JOSE ORTIZ | DOT TRAFFIC | REVIEW | Denied | February 15, 2008 ACTIVITY NUMBER: T08PI00003 PROJECT NAME: Sun Tran BSMF-Phase 2 PROJECT ADDRESS: 1911 W Price St PROJECT REVIEWER: Jose E. Ortiz PE, Traffic Engineer Resubmittal Required: Traffic Engineering does not recommend approval of the PIA Plan; therefore a revised PIA Plan is required for re-submittal. The following items must be revised or added to the plan. 1. Include a response letter with the next submittal that states how all comments have been addressed. 2. No striping required along local roads, therefore remove centerline striping, cross walk, and stop lines along Smoot Drive. Fire hydrant indicators can remain in design. 3. Install D3-1 (Street Name sign) with the proposed stop sign per PCDOT & TDOT Signing Manual (2002) Chap 5-11, 5-12, and Chap 9-2. 4. Install a W14-2a (No Outlet) plaque beneath the street name signs. 5. Install R2-1 (25MPH Speed Limit Sign) per PCDOT & TDOT Signing Manual (2002) Chap 9-10. 6. Parking is not allowed in cul-de-sacs from PRC to the point opposite the PRC. So indicate on the plans by showing no parking signs on the plans. (DS 3-01.0 fig 21) (bent cul). Provide a detail of the No Parking sign to be used. There is one attached to the red line plan set. 7. Place the PIA and CDRC Case number on the cover sheet. 8. Add the following Signing General Notes 5(a) & 5(b) per PCDOT & TDOT Signing Manual (2002) (Chapter 1, Sheet 12) to the Plans. 9. Add the following Pavement Marking/Striping General Notes to the Plans: 'ALL STREET STRIPING & SIGNAGE TO BE COORDINATED WITH C.O.T. TRAFFIC ENGINEERING CALL 791-4259 A MINIMUM OF 48 HOURS PRIOR TO THE INSTALLATION OR REMOVAL OF ANY SIGNAGE OR STRIPING. ALL REQUIRED STRIPING AND SIGNAGE WILL BE INSTALLED AT THE CONTRACTOR'S EXPENSE. NEW STRIPING TO BE THERMOPLASTIC MATERIAL. USE 2" SQUARE-TUBE POST AND SQUARE TUBE POST FOUNDATIONS FOR SIGNING. BARRICADE PLAN MUST BE SUBMITTED TO THE CITY OF TUCSON TRAFFIC ENGINEERING FOR APPROVAL 48 HOURS IN ADVANCE OF ANY WORK IN PUBLIC RIGHT OF WAY.' 'ALL NON-SIGNALIZED INTERSECTION STREET NAMES MUST HAVE E-W BLOCK NUMBER ADDRESSES FOR E-W ROADWAYS AND N-S BLOCK NUMBER ADDRESSES FOR N-S ROADWAYS.' If you have any questions, I can be reached at 791-4259 x76730 or Jose.Ortiz@tucsonaz.gov |
02/25/2008 | SMONTIE1 | PIA COORDINATOR | OUT TO CUSTOMER | Completed |