| 10/24/2008 | DAVE MANN | FIRE | REVIEW | Denied | The entire build must have sprinklers. Change not on Sheet SP1.0. Show location of nearest fire hydrant. Please include the following design criteria to the plans. 1. Flow data (static pressure, residual pressure, GPM) Available from the Fire Department (520) 791-3234 2. The standard to be used in development of sprinkler system. (NFPA 13, NFPA 13R, or NFPA 13D) 3. The hazard classification of the building, including any special hazards. 4. The density required of the water supply. |
| 10/24/2008 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Denied | 1. REFER TO NOTES ON PROJECT T08CM03458. |
| 10/24/2008 | JOHN WILLIAMS | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Completed | |
| 10/31/2008 | RAY MAJUTA | ELECTRICAL-COMMERCIAL | REVIEW | Approved | |
| 11/03/2008 | TERRY STEVENS | ZONING | REVIEW | Denied | 11/03/2008 Development Services Department Zoning Review Section Terry Stevens Lead Planner Comments: 1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed. 2. Zoning could not verify that the building plan was in compliance with the approved site plan. Please submit two copies of the approved and stamped site, landscape, and NPPO plans with the next building plan submittal. 3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved site plan. Additional comments may be forthcoming. |
| 11/06/2008 | GERRY KOZIOL | WWM | REVIEW | Denied | NEEDS TO SHOW LOCATION/METHOD OF CONNECTION TO PUBLIC SEWER |
| 11/18/2008 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Revise the font size used on the drawings to a minimum of 1/8-inch (all upper case). (A 3/32" font may be allowed with an appeal to the building official.) Reference: Section 106.1.1, IBC 2006. 2. Provide a site drawing showing the size, route, slope, and cleanout locations for the building sewer. Reference: Section 103.2.3, UPC 2006. 3. Provide water supply isometrics for the apartments. Reference: Section 103.2.3, UPC 2006. 4. If the two apartment buildings (A and B) are to be served by a common building sewer, the total flow for the private sewage collection system for this project will be in excess of 3000 gallons per day. The design for the system must be submitted to the Pima County Department of Environmental Quality for their approval prior to obtaining a permit for constructing the sewage collection system from the City of Tucson. A separate plumbing permit is required for the installation of a site sewer collection system. Reference: A.R.S. 49-104 (B) (13). 5. If the building owner wishes to select fixtures that have not been specified on the drawings, note that all plumbing fixtures and fittings shall be listed or labeled by a nationally-recognized, accredited conformity assessment company (e.g. UL, ETL, UPC, etc). Reference: Section 301.1.1, UPC 2006. 6. Provide information to show that the shower and tub/shower control valves conform to the requirements of ASSE 1016. Reference: Section 418.0, UPC 2006 7. Show the water supply to the dishwashers in the apartments. Reference: Sections 103.2.3 and 610.1, UPC 2006. 8. Coordinate the location of the water heater with the architectural drawings (A2.0). Reference: Section 103.2.3, UPC 2006. 9. Provide the manufacturer's specifications for the proposed storage water heater. Reference: Section 103.2.3, UPC 2006. 10. Provide a trap for P4 and clarify how the waste pipe from P4 connects to the building drain in the waste & vent riser diagram on sheet P2.0. Reference: Sections 103.2.3, 804.1, and 908.0, UPC 2006. 11. Provide a fullway CW shut off valve for each building entrance. Reference: Section 605.2, UPC 2006 12. Provide water pressure and water pipe sizing calculations. (Note that there are 2 hose bibbs shown on the plumbing plans but only one on the schedule.) Reference: Section 610.1, UPC 2006. 13. Clarify the note "1/2" CW DOWN TO WC INVERT 3' BELOW FFE" shown on sheet P1.0. Reference: Section 103.2.3, UPC 2006. 14. Clarify why CW and HW appear to be supplied to what looks like a furnace on sheet P1.0. Reference: Section 103.2.3, UPC 2006. 15. Provide specifications and details to show how the fire-rating will be preserved at the combustible and non-combustible piping penetrations of the fire-rated wall assembly. Reference: Section 1502.0, UPC 2006. |
| 11/18/2008 | ROBERT SHERRY | WATER | REVIEW | Denied | Provide a site drawing showing the size and route of the building water supply along with the location and size of both the site water meter and the site reduced pressure backflow preventer assembly. If the water meters for each apartment are to be provided by Tucson Water, provide the water supply drawings approved by Tucson Water. Reference: Section 103.2.3, UPC 2006. |
| 11/19/2008 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. The 2006 International Mechanical Code with Local Amendments is the relevant mechanical code for this project. See sheet G1.0 for the rest of the appropriate codes. 2. Revise the font size used on the drawings to a minimum of 1/8-inch (all upper case). Reference: Section 106.1.1, IBC 2006. 3. Provide energy code compliance calculations. Reference: Section 101.4, International Energy Conservation Code 2006. 4. Provide supporting documentation for the assembly U-factors for the windows along with the SHGC for the windows. Reference: Section 104.2, IECC 2006. 5. Unless the bathroom exhaust fans are operating continuously, the minimum exhaust flow rate shall be 50 CFM per bathroom. Reference: Section 403.3, IMC 2006. 6. Show the size, routing, and termination of the condensate drains for each fan coil unit. Reference: Section 307.2, IMC 2006 and Section 814.0, UPC 2006. 7. Provide ventilation for the restroom in the office. Reference: Section 403.3, IMC 2006. |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 11/24/2008 | VFLORES1 | OUT TO CUSTOMER | Completed |