Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL
Permit Number - T08CM03458
Review Name: RESUBMITTAL
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 01/05/2009 | ROBERT SHERRY | WATER | REVIEW | Approved | |
| 01/05/2009 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Adding a note (P-3 in the fixture schedule, P2.0) for the contractor to "provide handle position stops at hot water control" is not adequate by itself; include the requirement that the shower valves be listed as conforming to ASSE 1016. Reference: Section 418.0, UPC 2006 2. Comment not resolved. Coordinate the location of the water heater in the architectural drawing, A2.0, with the plumbing, mechanical, and the other architectural drawings (the electrical floor plan E1.0 just has the fan coil and the washer/dryer reversed). Reference: Section 103.2.3, UPC 2006. 3. Comment not resolved; the specified water heater model is not included in the manufacturer's literature. Provide the manufacturer's specifications for the proposed storage water heater. Reference: Section 103.2.3, UPC 2006. 4. Correct the water pressure and water pipe sizing calculations to correspond to the current project. (Note that the developed length is over 400 feet and the lift is over 18 feet.) Reference: Section 610.1, UPC 2006. |
| 01/05/2009 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. Revise the energy code compliance calculations, using the correct location (Pima County < 4,000 feet, not Phoenix) and using the correct areas (note that the length dimension for the second floor, as shown on sheet A2.1 is incorrect). Reference: Section 101.4, International Energy Conservation Code 2006. 2. Show the location and termination of the dryer exhaust duct. Reference: Sections 504.4 and 504.6.2, IMC 2006. |
| 12/12/2008 | DAVE MANN | FIRE | REVIEW | Approved | |
| 12/15/2008 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Denied | 1. PREVIOUS NOTE FROM 'PLUMBING COMMENTS' INDICATES "ALL" LETTERING SHALL BE 1/8" UNLESS A WRITTEN APPEAL FOR 3/32" LETTERING IS APPROVED BY THE BUILDING OFFICIAL, JESSIE SANDERS. THIS SET STILL INCLUDES MANY SHEETS THAT HAVE LETTERING LESS THAN 1/8" IN HEIGHT. THE APPROVED APPEAL MUST ACCOMPANY THE DRAWINGS SUBMITTED FOR CHECKING. 2. PREVIOUS COMMENT 2: MAKE THE SECTION CUTS (1 THROUGH 6 ON A6.0) ON THE PLANS OF SHEETS A1.0, A2.0, A2.1, A3.0, AND A3.1). THESE CUTS WILL ASSIST THE BUILDER AS WELL AS CITY INSPECTORS. |
| 12/16/2008 | TERRY STEVENS | ZONING | REVIEW | Denied | 12/16/2008 Development Services Department Zoning Review Section Terry Stevens Lead Planner Comments: 1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed. 2. Zoning could not verify that the building plan was in compliance with the approved site plan. Please submit two copies of the approved and stamped site, landscape, and NPPO plans with the next building plan submittal. 3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved site plan. Additional comments may be forthcoming. |
| 12/26/2008 | GERRY KOZIOL | WWM | REVIEW | Denied | NEEDS TO SHOW LOCATION/METHOD OF CONNECTION TO PUBLIC SEWER |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 01/07/2009 | GERARDO BONILLA | OUT TO CUSTOMER | Completed |
| 01/07/2009 | GERARDO BONILLA | REJECT SHELF | Completed |