Permit Number: T08CM03458
Parcel: 11307198B

Review Status: Completed

Review Details: RESUBMITTAL

Permit Number - T08CM03458
Review Name: RESUBMITTAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
01/05/2009 ROBERT SHERRY WATER REVIEW Approved
01/05/2009 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Denied 1. Adding a note (P-3 in the fixture schedule, P2.0) for the contractor to "provide handle position stops at hot water control" is not adequate by itself; include the requirement that the shower valves be listed as conforming to ASSE 1016. Reference: Section 418.0, UPC 2006
2. Comment not resolved. Coordinate the location of the water heater in the architectural drawing, A2.0, with the plumbing, mechanical, and the other architectural drawings (the electrical floor plan E1.0 just has the fan coil and the washer/dryer reversed). Reference: Section 103.2.3, UPC 2006.
3. Comment not resolved; the specified water heater model is not included in the manufacturer's literature. Provide the manufacturer's specifications for the proposed storage water heater. Reference: Section 103.2.3, UPC 2006.
4. Correct the water pressure and water pipe sizing calculations to correspond to the current project. (Note that the developed length is over 400 feet and the lift is over 18 feet.) Reference: Section 610.1, UPC 2006.
01/05/2009 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Denied 1. Revise the energy code compliance calculations, using the correct location (Pima County < 4,000 feet, not Phoenix) and using the correct areas (note that the length dimension for the second floor, as shown on sheet A2.1 is incorrect). Reference: Section 101.4, International Energy Conservation Code 2006.
2. Show the location and termination of the dryer exhaust duct. Reference: Sections 504.4 and 504.6.2, IMC 2006.
12/12/2008 DAVE MANN FIRE REVIEW Approved
12/15/2008 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Denied 1. PREVIOUS NOTE FROM 'PLUMBING COMMENTS' INDICATES "ALL" LETTERING SHALL BE 1/8" UNLESS A WRITTEN APPEAL FOR 3/32" LETTERING IS APPROVED BY THE BUILDING OFFICIAL, JESSIE SANDERS. THIS SET STILL INCLUDES MANY SHEETS THAT HAVE LETTERING LESS THAN 1/8" IN HEIGHT. THE APPROVED APPEAL MUST ACCOMPANY THE DRAWINGS SUBMITTED FOR CHECKING.
2. PREVIOUS COMMENT 2: MAKE THE SECTION CUTS (1 THROUGH 6 ON A6.0) ON THE PLANS OF SHEETS A1.0, A2.0, A2.1, A3.0, AND A3.1). THESE CUTS WILL ASSIST THE BUILDER AS WELL AS CITY INSPECTORS.
12/16/2008 TERRY STEVENS ZONING REVIEW Denied 12/16/2008

Development Services Department
Zoning Review Section

Terry Stevens
Lead Planner

Comments:

1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed.

2. Zoning could not verify that the building plan was in compliance with the approved site plan. Please submit two copies of the approved and stamped site, landscape, and NPPO plans with the next building plan submittal.

3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved site plan. Additional comments may be forthcoming.
12/26/2008 GERRY KOZIOL WWM REVIEW Denied NEEDS TO SHOW LOCATION/METHOD OF CONNECTION TO PUBLIC SEWER

Final Status

Task End Date Reviewer's Name Type of Review Description
01/07/2009 GERARDO BONILLA OUT TO CUSTOMER Completed
01/07/2009 GERARDO BONILLA REJECT SHELF Completed