Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL NEW
Permit Number - T08CM02805
Review Name: COMMERCIAL NEW
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 08/19/2008 | DAVE MANN | FIRE | REVIEW | Denied | Please include the following design criteria to the plans. 1. Flow data (static pressure, residual pressure, GPM) Available from the Fire Department (520) 791-3234 2. The standard to be used in development of sprinkler system. (NFPA 13, NFPA 13R, or NFPA 13D(for each part)) 3. The hazard classification of the building, including any special hazards. 4. The density required of the water supply. |
| 08/20/2008 | RONALD BROWN | ZONING HC SITE | REVIEW | Approved | |
| 08/20/2008 | RONALD BROWN | BUILDING-COMMERCIAL | REVIEW | Approved | |
| 08/20/2008 | RBROWN1 | ADA | REVIEW | Passed | NOT A COT PROJECT |
| 08/26/2008 | ROBERT SHERRY | WATER | REVIEW | Denied | 1. Clarify the water service to the building; the site drawing indicates two separate water service lines (as do the plumbing drawings) but shows a single water meter. In addition, the 2" water service is called out as a fire sprinkler riser. 2. Reduced pressure backflow prevention assemblies are required at the water meter for multi-use commercial buildings. Reference: COT Ordinance 9976, http://www.tucsonaz.gov/water/docs/backflow-ord.pdf |
| 08/27/2008 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | Provide energy code compliance calculations for a new commercial building. Reference: Section 101.4, International Energy Conservation Code 2006 |
| 08/27/2008 | TERRY STEVENS | ZONING | REVIEW | Denied | 08/27/2008 Development Services Department Zoning Review Section Terry Stevens Lead Planner Comments: 1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed. 2. Zoning could not verify that the building plan was in compliance with the approved development plan. Please submit two copies of the approved and stamped development, landscape, and NPPO plans with the next building plan submittal. 3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved site/development plan. Additional comments may be forthcoming. |
| 08/27/2008 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. The applicable code for all commercial plumbing projects is the 2006 Uniform Plumbing Code with Local Amendments. 2. Provide water supply isometrics. Reference: Section 103.2.3, UPC 2006. 3. Provide material standards for all plumbing fixtures being selected by the owner. Reference: Section 401.1, UPC 2006. 4. Provide CW shut off valves for each building entrance. Reference: Section 605.2, UPC 2006. 5. Provide water pressure and water pipe sizing calculations. Reference: Section 610.1, UPC 2006. 6. Calculate the water demand using the fixture units shown in Tables 6-5 or A-2. Reference: Section 610.3, UPC 2006. 7. Coordinate the water service piping for the irrigation system, for both size and layout, with the plumbing drawings. 8. Specify the materials to be used for the drainage piping and fittings (i.e. what is ABS 50-40?). Reference: Section 701.0, UPC 2006. 9. Provide a schedule of waste fixture units for all plumbing fixtures using the values shown in table 7-3, UPC 2006. Include the total number of each fixture being installed. Reference: Section 703.1, UPC 2006. 10. Provide the rim elevation of the next upstream sanitary manhole (it is not shown on the site plan) and the first floor elevation. Determine the need for a backwater valve per Section 710.1, UPC 2006, as amended by the City of Tucson. 11. Provide roof drainage calculations and clarify the roof design. Reference: Section 1106.0, UPC 2006. |
| 09/04/2008 | RAY MAJUTA | ELECTRICAL-COMMERCIAL | REVIEW | Approved | |
| 09/10/2008 | GERRY KOZIOL | WWM | REVIEW | Approved | |
| 09/10/2008 | BETH GRANT | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Completed |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 09/11/2008 | CPIERCE1 | OUT TO CUSTOMER | Completed |
| 09/11/2008 | SUE REEVES | REJECT SHELF | Completed |