Permit Number: T08CM02542
Parcel: 14111027A

Review Status: Completed

Review Details: POST 3RD PARTY REVIEW

Permit Number - T08CM02542
Review Name: POST 3RD PARTY REVIEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
12/16/2008 STEVE SHIELDS ZONING REVIEW Needs Review 12/16/2008

Development Services Department
Zoning Review Section

Steve Shields
Lead Planner

Comments:

1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed.

2. Zoning could not verify that the building plan was in compliance with the approved development plan. Please submit two copies of the approved and stamped development, landscape, and NPPO plans with the next building plan submittal.

3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved site/development plan. Additional comments may be forthcoming.
12/18/2008 GERRY KOZIOL WWM REVIEW Denied need to review location & method of connection to public sewer
12/19/2008 JASON GREEN ENGINEERING REVIEW Denied DATE: December 19, 2008
SUBJECT: 7575 S Old Vail Road Building Plan- 2nd Engineering Review
TO: John Feneck
LOCATION: T15S R15E Sec21 Ward 4
REVIEWERS: Jason Green, CFM
ACTIVITY: T08CM02542 (Building Plan)


SUMMARY: Engineering Division of Development Services Department has received the building plan (T08CM02542) for the above referenced property. Engineering Division does not recommend approval of the building plan application at this time. The following items need to be addressed:


BUILDING PLAN COMMENTS:

1) Engineering could not verify that the building plan was in compliance with the stamped approved development plan. Please submit two copies of the stamped approved development plan, landscape, and NPPO plans with the next building plan submittal. Engineering may not be able to approve the building plan until the development plan has been approved.

2) Engineering will re-review the building plan on the next submittal to insure compliance with the approved and stamped development plan. Additional comments may be forthcoming.


GENERAL COMMENTS:

Please provide a revised building plan that addresses the comments provided above. Include a comprehensive response letter addressing in detail responses to all of the above comments.

Further comments may be generated upon re-submittal of the building plan review.

If you have any questions or to schedule an appointment I can be reached at 837-4929.




Jason Green, CFM
Senior Engineer Associate
Engineering Division
COT Development Services

Final Status

Task End Date Reviewer's Name Type of Review Description
12/23/2008 CPIERCE1 OUT TO CUSTOMER Completed
12/23/2008 SUE REEVES REJECT SHELF Completed