Permit Review Detail
Review Status: Completed
Review Details: 3RD PARTY REVIEW-COMMERCIAL TI
Permit Number - T08CM02293
Review Name: 3RD PARTY REVIEW-COMMERCIAL TI
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 07/14/2008 | STEVE SHIELDS | ZONING | REVIEW | Denied | DSD TRANSMITTAL FROM: Steve Shields Lead Planner PROJECT: Copper/State Bolt & Nut Co. T.I. T08CM02293 Building Plan (1st Review) TRANSMITTAL DATE: July 14, 2008 1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan until all zoning comments or concerns have been addressed. 2. Zoning could not verify that the building plan was in compliance with the approved site plan. Please submit two copies of the approved and stamped site, landscape, and NPPO plans with the next building plan submittal. 3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved and stamped site plan. Additional comments may be forthcoming. If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956 C:\planning\grading\t08cm02293.doc RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised site plan and additional requested documents |
| 07/28/2008 | VFLORES1 | WWM | REVIEW | Needs Review | |
| 07/28/2008 | BETH GRANT | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Needs Review | |
| 07/28/2008 | STANTEC | 3RD PARTY REVIEW-COMMERCIAL | REVIEW | Completed | |
| 07/28/2008 | BIANCA RAMIREZ | ENGINEERING | REVIEW | Needs Review | |
| 07/28/2008 | VFLORES1 | WATER | REVIEW | Needs Review | |
| 07/28/2008 | VFLORES1 | FIRE | REVIEW | Needs Review | |
| 07/28/2008 | VFLORES1 | 3RD PARTY REVIEW-COMMERCIAL | AT 3RD PARTY OFFICE | Approved |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 07/28/2008 | VFLORES1 | OUT TO CUSTOMER | Completed |