Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL
Permit Number - T08CM00804
Review Name: RESUBMITTAL
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 05/30/2008 | DAVE MANN | FIRE | REVIEW | Denied | A separate permit for the installation of fuel tanks is required through the Fire Department. We will need three copies of the tank installation details, all relevant cut sheets for the materials, and a permit application. Sheet A-1 the hydrant shown as existing is not shown on Tucson Water maps. Sheet F2 The vapor recover plans show the VR line running to the red diesel, not the unleaded. See IFC 3404.2.7.3.5.3. Sheet E2 The emergency shut off is less than 20" from the dispenser on drive side. IFC 2203.3. |
| 06/02/2008 | HEATHER THRALL | ZONING | REVIEW | Denied | When the site plan has been approved by all divisions, and the building plans approved by structural - the building plans can be brought through the zoning review counter for continued review. |
| 06/06/2008 | LINDA BUCZYNSKI | ELECTRICAL-COMMERCIAL | REVIEW | Denied | TRANSMIT ORIGINAL DRAWINGS WITH NEXT SUBMITTAL. PLEASE CALL AT 520.837.4907 OR EMAIL AT Linda.Buczynski@tucsonaz.gov IF YOU CARE TO DISCUSS. 1. Provide for bonding of the metal building according to the requirements of NEC 250.104 (C). 2. Revise the font size used on the drawings to a minimum of 1/8-inch (all upper case). Reference Section 106.1.1, IBC 2006. 3. Put compact fluorescent fixtures on the Luminaire Schedule, and add the exterior on to the compliance calculations for outdoor lighting. 4. Add a note on the plans: "Special Inspection required for exterior lighting fixtures per Tucson Lighting Code Section 16." 5. Provide an electrical circuit(s) for the CCTV. 6. Provide a disconnecting means for the fuel pumps. 7. Please remove the redundant #4 GND between the meter and the utility transformer. The fourth 4/0 conductor will convey any fault current back to the source on the line side of the service disconnecting means. 8. Please specify that the conduit for Fixtures B shall be sealed at both ends. Similar to the direction provided on Sheet E1, Keynotes 1,2, and 5.9. Provide exact specification for the type |
| 06/23/2008 | PAUL MACHADO | ENGINEERING | REVIEW | Denied | See Site plan comments. |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 09/18/2008 | CINDY AGUILAR | OUT TO CUSTOMER | Completed |
| 09/18/2008 | SUE REEVES | REJECT SHELF | Completed |