Review Details: POST 3RD PARTY REVIEW
Permit Number - T08CM00749
Review Name: POST 3RD PARTY REVIEW
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
08/27/2008 | JOHN WILLIAMS | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Passed | |
08/28/2008 | STEVE SHIELDS | ZONING | REVIEW | Denied | DSD TRANSMITTAL FROM: Steve Shields Lead Planner PROJECT: Target Out Parcel - 4020/4022 N. Oracle T08CM00748 & 749 Building Plan (1st Review) TRANSMITTAL DATE: August 28, 2008 1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan until all zoning comments or concerns have been addressed. 2. Zoning could not verify that the building plan was in compliance with the approved/stamped development plan. Please submit two copies of the approved/stamped development, landscape, and NPPO plans with the next building plan submittal. 3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved and stamped site plan. Additional comments may be forthcoming. If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956 C:\planning\grading\t08cm00748.doc RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised site plan and additional requested documents |
08/28/2008 | DAVE MANN | FIRE | REVIEW | Approved | Fire Department Connection may require relocation. |
09/10/2008 | BIANCA RAMIREZ | ENGINEERING | REVIEW | Denied | DSD TRANSMITTAL FROM: Bianca Ramirez Engineering Associate PROJECT: Target Out Parcel - 4020/4022 N. Oracle T08CM00748 & 749 Building Plan (1st Review) TRANSMITTAL DATE: September 10, 2008 1. The building plan has been reviewed by Engineering Review Section but cannot approve the plan until all zoning comments or concerns have been addressed. 2. Unable to verify that the building plan was in compliance with the approved/stamped development plan. Please submit two copies of the approved/stamped development, landscape, and NPPO plans with the next building plan submittal. 3. Engineering will re-review the building plan on the next submittal once zoning has verified compliance with the approved and stamped site plan. 4. Additional comments may be forthcoming. If you have any questions about this transmittal, please contact me at bianca.ramirez@tucsonaz.gov or (520) 837-4956 |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
09/18/2008 | CPIERCE1 | OUT TO CUSTOMER | Completed |
09/18/2008 | SUE REEVES | REJECT SHELF | Completed |