Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL TI
Permit Number - T08CM00508
Review Name: COMMERCIAL TI
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 04/02/2008 | MARTIN BROWN | FIRE | REVIEW | Approved | |
| 04/02/2008 | RAY MAJUTA | ELECTRICAL-COMMERCIAL | REVIEW | Approved | |
| 04/02/2008 | JOHN WILLIAMS | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Passed | |
| 04/08/2008 | RONALD BROWN | BUILDING-COMMERCIAL | REVIEW | Denied | 1. IDENTIFY PROPERLY ALL THREE SPACES AND ASSOCIATED SUITE NUMBERS 2. REVISE BUILDING DATA PER INDIVIDUAL SUITE NUMBERS 3. NEED FURTHER INFORMATION AND DETAILING FOR MOUNTING OF HVAC UNITS. PROVIDE DETAIL SHOWING CONNECTION TO EXISTING RIDGE BEAM AND SLOPED ROOF JOISTS 4. PROVIDE DETAILING AND STRUCTURAL CALCULATIONS FOR INTERIOR PARTITIONING |
| 04/17/2008 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. Provide mechanical plans (see details 1/M1.1 and 2/M1.1) with a legible background. Reference: Section 106.3.1, IMC 2006. 2. Complete recirculation of ventilation air from toilet rooms is prohibited. If the exhaust fans are switched off during occupied hours, where will the supply air to the restrooms go? Reference: Section 403.2.1 (3), IMC 2006. 3. Specify the minimum resistance (R-value) of the duct insulation to be used on this project. Reference: Section 503.2.7, IECC 2006, as amended by the City of Tucson. |
| 04/17/2008 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Provide plumbing plans (see detail 1/P1.1) with a legible background. Reference: Section 103.2.3, UPC 2006. 2. Provide a vacuum relief for storage-type water heaters located above any fixture outlets. Reference: Section 608.7, UPC 2006. |
| 04/17/2008 | ROBERT SHERRY | WATER | REVIEW | Approved | |
| 04/29/2008 | GERRY KOZIOL | WWM | REVIEW | Denied | 1:Sears Financial corp 2:needs to show location/method of connection to public sewer 3:property does not front public sewer-needs wastewater 8th floor review of location/method of connection to public sewer 4:needs wastewater 8th floor review of easement/joint use sewer agreements if applicable |
| 05/05/2008 | STEVE SHIELDS | ZONING | REVIEW | Approved | |
| 05/07/2008 | BIANCA RAMIREZ | ENGINEERING | REVIEW | Approved |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 05/09/2008 | VFLORES1 | OUT TO CUSTOMER | Completed |
| 05/09/2008 | SUE REEVES | REJECT SHELF | Completed |