Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL TI
Permit Number - T08CM00207
Review Name: COMMERCIAL TI
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
02/06/2008 | MICHAEL ST. PAUL | ZONING | REVIEW | Approved | |
02/06/2008 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | Clarify how the ventilation is to be provided for this suite; natural ventilation (sheet M1.1) or mechanical ventilation (M2.1). |
02/06/2008 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Show how the drinking fountain (P4) complies with the accessibility requirements of Section 1109.5, IBC 2006. 2. Clarify the difference in the building drain layout shown in the TI as compared to the building drain shown on the shell drawing. 3. Provide information to show that freeze protection is not required for the water piping located in the warehouse (e.g. mop sink, drinking fountain, and the water supply to the evaporative cooler). |
02/06/2008 | ROBERT SHERRY | WATER | REVIEW | Approved | |
02/06/2008 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Denied | 1. REVIEW SQUARE FOOTAGE SHOWN ON SHEET A0. SQUARE FOOTAGE USED IN OCCUPANCY CALCULATION DOES NOT AGREE WITH GENERAL BUILDING SUMMARY. 2. REVIEW OCCUPANCY CLASSIFICATIONS. USING MERCANTILE FOR FIRST FLOOR AND MEZZANINE WILL SAVE USING FIRE SEPARATION WALL. 3. REVIEW CALCULATIONS FOR NUMBER OF OCCUPANTS ALLOWED. 4. NOTES 9 AND 10 ON PLAN 1, SHEET A2.1, SHOULD BE REVERSED. 5. BUILDING CODE REQUIRES HIGH/LOW DRINKING FOUNTAIN, OR YOU CAN APPLY FOR A VARIANCE FROM THE BUILDING OFFICIAL TO USE A WATER BOTTLE. 6. SHEET A7, ELEVATION 18: SPECIFY WATER RESISTANT WALL SURFACE TO BE USED. 7. DEMOLITION PLAN REQUIRED FOR REMOVAL OF EXISTING FLOOR SLAB AT NEW FOOTINGS. 8. STRUCTURAL CALCULATIONS REQUIRED FOR NEW UNITS AND/OR OPENINGS ON EXISTING STRUCTURE. |
02/06/2008 | JASON GREEN | ENGINEERING | REVIEW | Approved | |
02/07/2008 | LINDA BUCZYNSKI | ELECTRICAL-COMMERCIAL | REVIEW | Approved | |
02/08/2008 | MARTIN BROWN | FIRE | REVIEW | Approved | |
02/13/2008 | GBONILL1 | WWM | REVIEW | Needs Review | |
02/13/2008 | BETH GRANT | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Needs Review |