Permit Number: T08BU00687
Parcel: 11942009C

Review Status: Completed

Review Details: GRADING

Permit Number - T08BU00687
Review Name: GRADING
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
04/21/2008 ELIZABETH EBERBACH ENGINEERING REVIEW Approved DATE: April 30, 2008
TO: DOWL Engineers
SUBJECT: Riverfront Plaza (S07-101) Grading Plan Engineering Review
LOCATION: T14S R13E Section 35, 119-42-009C
REVIEWER: Elizabeth Eberbach
ACTIVITY NUMBER: T08BU00687

SUMMARY: The Grading Plans, geotechnical report, SWPPP and Drainage Report were received by Engineering. A meeting was held April 3 and April 9, 2008 at request of consultant to discuss grading plan submittal. Engineering has reviewed the received items and recommends approval of the grading plan. The Drainage Report was reviewed for grading plan purposes only.

GRADING PERMIT CONDITIONS:
THE FOLLOWING 24 CONDITIONS APPLY TO PERMIT T08BU00687:
1) CALL FOR PRE-CONSTRUCTION MEETING, INTERMEDIATE AND FINAL INSPECTIONS. FOR A DSD ENGINEERING INSPECTION, CALL IVR (740-6970), OR CONTACT DSD ENGINEERING AT 837-4888, OR SCHEDULE INSPECTIONS ONLINE AT: HTTP://WWW.CI.TUCSON.AZ.US/DSD/ONLINE_SERVICES/ONLINE_PERMITS/ONLINE_PERMITS.HTML
2) FOR INSPECTION PURPOSES, PLEASE POST THE "AZPDES - POSTING REQUIREMENTS" GREEN SHEET AT CONSTRUCTION ENTRANCE OF THE SITE AT BEGINNING OF CONSTRUCTION ACTIVITIES AND MAINTAIN THIS POSTED DOCUMENT THROUGHOUT PROJECT CONSTRUCTION.
3) THIS GRADING PLAN AND SWPPP ARE FOR CLEARING, UTILITY INFRASTRUCTURE, PAVING AND LANDSCAPING ASSOCIATED WITH RIVERFRONT PLAZA DEVELOPMENT PLAN (S07-101) AS SHOWN ON THE APPROVED GRADING PLAN T08BU00687 SEALED BY JESUS LORENZO ORTIZ DATED 4/08/08, AND GEOTECHNICAL REPORT FROM GRC AND ASSOCIATED ADDENDA, AND DRAINAGE REPORT SEALED BY ROBERT W LANE DATED 2/28/08.
4) A COPY OF THE NOI, STORMWATER POLLUTION PREVENTION PLAN (SWPPP), GRADING PLAN AND GRADING PERMIT SHALL BE KEPT AT THE SITE AT ALL TIMES, UNTIL FINAL GRADING APPROVAL.
5) IMPROVEMENTS EXCLUDE GRADING CONSTRUCTION FOR BUILDING PADS 1-4. SEE OTHER PERMITS FOR INDIVIDUAL PAD DEVELOPMENT.
6) PERMANENT EROSION AND SEDIMENT CONTROLS ARE REQUIRED PER LUC CODE AND OTHER CITY REQUIREMENTS. INDIVIDUAL PAD AREAS SHALL BE RE-SEEDED, COVERED WITH ROCK, OR OTHERWISE MATERIAL ACCEPTED BY THE CITY DSD ENGINEERING AND LANDSCAPING PRIOR TO CLOSING THIS PERMIT ACTIVITY.
7) TEMPORARY EROSION/STORMWATER CONTROLS MAY BE FIELD ADJUSTED WITH DISCUSSIONS WITH OPERATORS AND ENGINEER OF RECORD AS NECESSARY ALONG DISTURBANCE LIMITS FOR THIS PROJECT.
8) DESIGNATED CONCRETE WASHOUT LOCATIONS ARE REQUIRED AND SHALL NOT BE LOCATED IN OR NEAR THE BASIN OR WATER HARVESTING AREAS. LOCATION OF TEMPORARY MATERIAL OR VEHICLE STAGING / STOCKPILE AREA SHALL BE PLACED WITHIN GRADING LIMITS AND NOT LOCATED IN ANY WATER HARVESTING OR BASIN AREAS.
9) CONTACT PERMITS AND CODES (791-5100) FOR ANY QUESTIONS REGARDING ANY RIGHT-OF-WAY PERMIT REQUIREMENTS.
10) DUST CONTROL METHODS SUCH AS WATER TRUCK WILL BE PROVIDED, AS WELL AS DAILY SWEEPING OF THE STREETS.
11) REVISED CONSTRUCTION PHASING DIAGRAM INFORMATION SHALL BE PROVIDED IN THE FIELD AND / OR BY A PLAN TO IDENTIFY CONSTRUCTION TRAFFIC CONTROLS DIFFERENTIATING RESTAURANT PUBLIC ACCESS AND CONSTRUCTION TRAFFIC FOR LOT 1 / BUILDING PAD #4.
12) TRAFFIC SIGNAGE FOR CONSTRUCTION VEHICLE RESTRICTIONS SHALL BE PLACED AT CENTRAL ENTRANCE TO SITE TO ASSURE RESTAURANT PUBLIC ACCESS IS MAINTAINED AND CONSTRUCTION VEHICLES ARE PROHIBITED FROM ENTERING AT EAST ENTRANCE FROM IRVINGTON ROAD.
13) TEMPORARY CONSTRUCTION ENTRANCE SHALL BE EXTENDED TO PROPERTY BOUNDARY AT SOUTHWEST CORNER OF PROJECT ENTRANCE.
14) CALL FOR SPECIAL INSPECTION FOR CONSTRUCTION SIGNAGE AND FENCING. THIS MAY OCCUR AT SWPPP / PRECON INSPECTION.
15) THE NUMBER AND LOCATION OF TREES WITHIN EXISTING AND FUTURE SIGHT VISIBILITY TRIANGLES MAY BE RESTRICTED OR MODIFIED BY THE CITY OF TUCSON IN ORDER TO PRESERVE VISIBILITY.
16) THERE SHALL BE NO DISTURBANCE OUTSIDE OF THE APPROVED DISTURBANCE/GRADING LIMITS, AND THERE SHALL BE NO DISTURBANCE IN THE WEST BANK SANTA CRUZ RIVER (WBSCR) W.A.S.H. ORDINANCE STUDY AREA OR IN THE WBSCR OR SANTA CRUZ RIVER. STOP WORK ORDER MAY BE ISSUED FOR DISTURBANCE OF WASH AREAS.
17) NO GRADING SHALL BEGIN UNTIL ALL REQUIRED SWPPP CONTROLS ARE INSTALLED.
18) SEPARATE BUILDING PERMIT APPLICATIONS ARE REQUIRED FOR ANY WALLS.
19) ANY REVISION TO THE GRADING PLAN MAY REQUIRE A RE-SUBMITTAL OF A REVISED GRADING PLAN FOR REVIEW. CONTACT DSD ENGINEERING TO DISCUSS CHANGES IN GRADING DESIGN.
20) IF GRADING CONSTRUCTION IS EXPECTED TO LAST LONGER THAN THE EXPIRATION DATE OF THE GRADING PERMIT, CONTACT DSD TO RENEW/EXTEND THE GRADING PERMIT. IF FINAL GRADING INSPECTION HAS NOT BEEN COMPLETED BEFORE THE GRADING PERMIT EXPIRES, AND THE PERMIT HAS NOT BEEN RENEWED, ADDITIONAL FEES AND REVIEWS MAY BE REQUIRED.
21) PRIOR TO FINAL APPROVAL, AS-BUILTS MAY BE REQUIRED. LETTERS OF COMPLETION ARE REQUIRED.
22) PRIOR TO REQUEST FOR FINAL INSPECTION APPROVAL, ANY OUTSTANDING FEES SHALL BE PAID.
23) THE PERMITEE SHALL NOTIFY DSD WHEN THE GRADING OPERATION IS READY FOR FINAL GRADING INSPECTION. FINAL GRADING APPROVAL SHALL NOT BE GIVEN UNTIL ALL WORK, INCLUDING INSTALLATION OF ALL DRAINAGE IMPROVEMENTS ALONG PERIMETER, UTILITY TRENCHES ARE BACKFILLED, CENTRAL PAVING, PERMANENT PROTECTIVE DEVICES, ALL EROSION CONTROL MEASURES HAVE BEEN COMPLETED, AND ALL CONDITIONS OF PERMIT ARE COMPLETED.
24) PRIOR TO REQUEST FOR FINAL GRADING INSPECTION APPROVAL, ALL PERMANENT EROSION CONTROL IMPROVEMENTS SHALL BE INSTALLED AND ACCEPTED BY DSD INCLUDING ROCK / ESTABLISHED REVEGETATION FOR ALL DISTURBED AREAS IF NOT IMPROVED AS PER APPROVED PLAN.

If you have any questions, please call me at 837-4934.

Elizabeth Eberbach, PE
Civil Engineer
Engineering Division
Development Services

Final Status

Task End Date Reviewer's Name Type of Review Description
05/16/2008 SUE REEVES APPROVAL SHELF Completed
05/16/2008 DELMA ROBEY OUT TO CUSTOMER Completed