Permit Review Detail
Review Status: Completed
Review Details: PLANS OK TO SUBMIT - GRADING
Permit Number - T08BU00523
Review Name: PLANS OK TO SUBMIT - GRADING
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 08/05/2008 | STEVE SHIELDS | ZONING | REVIEW | Approved | |
| 08/05/2008 | STEVE SHIELDS | ZONING_QA | REVIEW | Passed | |
| 08/05/2008 | ELIZABETH EBERBACH | ENGINEERING | REVIEW | Approved | DATE: August 5, 2008 TO: George Holguin, RA, Steve Corrales, PE REVIEWER: Elizabeth Eberbach, PE, CPM, CFM SUBJECT: 3127 E ADAMS ST Site Plan and Grading Plan resubmittal reviews ACTIVITY NUMBER: T08CM00904, T08BU00523 SUMMARY: Engineering Division of Development Services Department has received and reviewed the revised site and grading plan resubmittal at the counter after meetings with the architect and professional engineer. During meetings, the registrants came in to resolve deficiencies in the drainage report and site and grading plans. Engineering recommends approval of the proposed site plan and grading permit for the area including improvements for proposed Building C.1 and the parking area east of existing Building J including minor improvements for landscaping/parking/striping in the northeast parking area. See the following conditions of the grading permit. CONDITIONS OF GRADING PERMIT: THE FOLLOWING 14 CONDITIONS APPLY TO PERMIT T08BU00523: 1) CALL FOR PRE-CONSTRUCTION MEETING, INTERMEDIATE AND FINAL INSPECTIONS. FOR A DSD ENGINEERING INSPECTION, CALL IVR (740-6970), OR CONTACT DSD ENGINEERING AT 837-4888, OR SCHEDULE INSPECTIONS ONLINE AT: HTTP://WWW.CI.TUCSON.AZ.US/DSD/ONLINE_SERVICES/ONLINE_PERMITS/ONLINE_PERMITS.HTML 2) THIS GRADING PLAN IS FOR CLEARING, PAVING, LANDSCAPING, AND DRAINAGE IMPROVEMENTS ASSOCIATED WITH THE SOUTHWEST BUILDING C.1, AS WELL AS MINOR IMPROVEMENTS FOR PARKING/LANDSCAPING/STRIPING EAST OF BUILDING J AS SHOWN ON THE APPROVED GRADING PLAN (T08BU00523). SEE SITE A D GRADING PLAN SHEETS CVR, SD-1, SD-2, C-1, AND C-2 SEALED BY GEORGE HOLGUIN RA AND STEVE CORRALES PE, (SHEETS SD-2AND C-2 DATED 8-4-08) AND DRAINAGE REPORT SEALED BY STEVE CORRALES PE DATED 7-29-2008. 3) TEMPORARY STORMWATER CONTROLS SUCH AS WATTLE OF SILT FENCE SHOULD BE CONSIDERED FOR INSPTALLATION AND MAINTENANCE AT DOWNSTREAM GRADING DISTURBANCE LIMITS. 4) CONTACT PERMITS AND CODES (791-5100) FOR ANY QUESTIONS REGARDING ANY RIGHT-OF-WAY PERMIT REQUIREMENTS. 5) DUST CONTROL METHODS SHOULD BE PROVIDED, INCLUDING DAILY SWEEPING OF THE STREETS. 6) SEPARATE BUILDING PERMIT APPLICATIONS ARE REQUIRED FOR ANY WALLS. 7) ADDITIONAL REVIEW / PERMITTING IS REQUIRED FOR OTHER IMPROVEMENTS OUTSIDE THE SCOPE OF THIS PERMIT. 8) CALL FOR DSD ENGINEERING INSPECTOR FOR SPECIAL INSPECTION OF PIPE INSTALLATION. 9) ANY REVISION TO THE GRADING PLAN MAY REQUIRE A RE-SUBMITTAL OF A REVISED GRADING PLAN FOR REVIEW. CONTACT DSD ENGINEERING TO DISCUSS CHANGES IN GRADING DESIGN. 10) IF GRADING CONSTRUCTION IS EXPECTED TO LAST LONGER THAN THE EXPIRATION DATE OF THE GRADING PERMIT, CONTACT DSD TO RENEW/EXTEND THE GRADING PERMIT. IF FINAL GRADING INSPECTION HAS NOT BEEN COMPLETED BEFORE THE GRADING PERMIT EXPIRES, AND THE PERMIT HAS NOT BEEN RENEWED, ADDITIONAL FEES AND REVIEWS MAY BE REQUIRED. 11) PRIOR TO FINAL APPROVAL, AS-BUILT PLAN AND LETTERS OF COMPLETION MAY BE REQUIRED. 12) PRIOR TO REQUEST FOR FINAL INSPECTION APPROVAL, ALL IMPROVEMNTS SHOULD BE COMPLETED AND SHALL BE PAID. 13) THE PERMITEE SHALL NOTIFY DSD WHEN THE GRADING OPERATION IS READY FOR FINAL GRADING INSPECTION. FINAL GRADING APPROVAL SHALL NOT BE GIVEN UNTIL ANY OUTSTANDING FEES ARE PAID, AND ALL WORK HAS BEEN COMPLETED, AND ALL PERMIT CONDITIONS ARE COMPLETED. 14) PRIOR TO REQUEST FOR FINAL GRADING INSPECTION APPROVAL, ALL PERMANENT EROSION CONTROL IMPROVEMENTS SHALL BE INSTALLED AND ACCEPTED BY DSD INCLUDING ROCK / ESTABLISHED REVEGETATION FOR ALL DISTURBED AREAS IF NOT IMPROVED AS PER APPROVED PLAN. If you have any questions, I can be reached at 837-4934. Elizabeth Eberbach, PE Civil Engineer Engineering Division Development Services |
| 08/05/2008 | ELIZABETH EBERBACH | ENGINEERING_QA | REVIEW | Passed | Drainage Report was unacceptable and made no sense. Several meetings with RA and PE required to resolved discrepancies in submittal documents. |