Permit Number: T08BU00103
Parcel: 116292470

Review Status: Active

Review Details: RESUBMITTAL - GRADING ALL

Permit Number - T08BU00103
Review Name: RESUBMITTAL - GRADING ALL
Review Status: Active
Review Date Reviewer's Name Type of Review Description Status Comments
02/10/2009 ANDREW CONNOR NPPO REVIEW Approv-Cond
02/24/2009 MICHAEL ST. PAUL ZONING REVIEW Approved
02/24/2009 ELIZABETH LEIBOLD ENGINEERING REVIEW Approv-Cond DATE: February 24, 2009
TO: Bruce Patton, PE, RICK Engineering
SUBJECT: Starr Pass Vistas Village 2 Grading Plan Resubmittal Engineering Review
LOCATION: T14S R13E Section 16
REVIEWER: Elizabeth Leibold
REFERENCE: S07-033, T08SA00089
ACTIVITY NUMBER: T08BU00103

SUMMARY: The Grading Plan package was reviewed by Engineering. Engineering recommends conditional approval of the Grading Plan. The following conditions apply to the grading permit.

GRADING PLAN CONDITION OF APPROVAL:
1) Submit Floodplain Use Permit application for approval prior to picking up grading permit.

GRADING PERMIT CONDITIONS:
The following 14 conditions apply to grading permit T08BU00103:
1) If grading permit is not picked up by 27MAR09, application will expire unless request for grading permit extension is submitted to Development Services Department (attn: Claudia Buford) for consideration of grading plan approval extended extension.
2) Any revisions to the private streets, or other aspects of the grading plan including gated entrance or drainage improvements, must be reviewed by the DSD Engineering Engineer and may include a revised grading plan. Call DSD Engineering at 791-5550 to discuss any revisions.
3) If grading construction is expected to last longer than the expiration date of the grading permit, contact DSD to renew/extend the Grading Permit. If Final Grading Inspection has not been completed before the Grading Permit expires, and the permit has not been renewed, additional fees and reviews may be required.
4) Special inspection required for toedowns or other subsurface structures.
5) Call for Pre-construction meeting once grading activity is expected to start. For a DSD Engineering Inspection, call IVR (740-6970), or schedule with a Customer Service Representative at the Development Services Department, or contact DSD Engineering at 837-4888, or schedule inspections online at: http://www.ci.tucson.az.us/dsd/Online_Services/Online_Permits/online_permits.html
6) Any revision to the Grading Plan may require a re-submittal of a revised grading plan for review. Contact DSD Engineering at 791-5550 to discuss changes in street / grading design.
7) City of Tucson grading standards to DS Sec.11-01 apply.
8) Receiving waters is the Silvercroft Wash (an ERZ Wash).
9) Grading / Disturbance Limits shall be maintained and no disturbance outside of grading limits will be allowed. Stop Work Order may be issued if disturbance occurs outside of approved grading limits as shown on the approved grading plans. There shall be no disturbance, construction vehicle traffic or parking, or stockpiling outside of the approved Grading Limits as shown on the Grading Plan. There shall be no disturbance of Silvercroft Wash. Any disturbance of Silvercroft Wash will result in Stop Work Order.
10) Separate grading permits are required for each lot. There shall be no grading on individual lots unless specifically indicated by grading limits as shown on the approved grading plans.
11) During construction activities, traffic controls are required to limit traffic hazards onto Greasewood Road and Starr Pass Boulevard.
12) Use of water trucks or other dust controls shall be utilized, and construction entrances shall be maintained to minimize sedimentation, dust issues, and tracking.
13) Stockpile area, concrete washout area, and storage areas shall be located away from the water harvest areas, basins or washes.
14) As-builts are required, with grading and basin completion documentation from project engineer at time of final inspections. Drainage structures including basin function will need substantial completion documentation. Field observations and soils reports from geotechnical engineer are required to be submitted at time of culvert construction and prior to final inspections. Street paving plan as-builts will also be required to be submitted prior to final grading approval.

If you have any questions, please call me at 837-4934.


Elizabeth Leibold, PE
Civil Engineer
Engineering Division
Development Services