Plan Review Detail
Review Status: Completed
Review Details: PIA SUBMITTAL
Plan Number - T07PI00045
Review Name: PIA SUBMITTAL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
01/10/2008 | GARY WITTWER | DOT LANDSCAPE | REVIEW | Denied | 1. NPPO has been approved. 2. You can not have a private irrigation line under the public roadway. You will need to get a easement for this and follow all of the requirements. Sch. 80 sleeve, provide marking tape, minimum 18" deep, stamp "IS" on curb above sleeve, extend 12" beyond curb edge, legal easement recorded. 3. Who is paying for water and maintenance of this area? |
01/10/2008 | SMONTIE1 | UTILITY CLEARANCES | COT STREETS DIVISION | Denied | PLEASE SUBMIT UTILITY CLEARANCE LETTERS |
01/10/2008 | JOSE ORTIZ | DOT TRAFFIC | REVIEW | Denied | January 23, 2008 ACTIVITY NUMBER: T07PI00045 PROJECT NAME: Vista Verde Estates PROJECT ADDRESS: 844 N Houghton Rd PROJECT REVIEWER: Jose E. Ortiz PE, Traffic Engineer Resubmittal Required: Traffic Engineering does not recommend approval of the PIA Plan; therefore a revised PIA Plan is required for re-submittal. The following items must be revised or added to the plan. 1. Include a response letter with the next submittal that states how all comments have been addressed. 2. See redlines on the submitted drawings and address the additional redline comments. During the next submittal please re-submit the roll of redlines for back checking purposes. 3. Provide a break in edgeline striping and the center two-way left turn lane per PCDOT & TDOT Pavement Marking Design Manual (2002) Chapter 3-5. Show existing striping in plan view to establish location of striping break. 4. Place the PIA and CDRC Case number on the cover sheet. 5. Add the following Pavement Marking/Striping General Notes to the Plans: 'ALL STREET STRIPING & SIGNAGE TO BE COORDINATED WITH C.O.T. TRAFFIC ENGINEERING CALL 791-4259 A MINIMUM OF 48 HOURS PRIOR TO THE INSTALLATION OR REMOVAL OF ANY SIGNAGE OR STRIPING. ALL REQUIRED STRIPING AND SIGNAGE WILL BE INSTALLED AT THE CONTRACTOR'S EXPENSE. NEW STRIPING TO BE THERMOPLASTIC MATERIAL. USE 2" SQUARE-TUBE POST AND SQUARE TUBE POST FOUNDATIONS FOR SIGNING. BARRICADE PLAN MUST BE SUBMITTED TO THE CITY OF TUCSON TRAFFIC ENGINEERING FOR APPROVAL 48 HOURS IN ADVANCE OF ANY WORK IN PUBLIC RIGHT OF WAY.' 'ALL NON-SIGNALIZED INTERSECTION STREET NAMES MUST HAVE E-W BLOCK NUMBER ADDRESSES FOR E-W ROADWAYS AND N-S BLOCK NUMBER ADDRESSES FOR N-S ROADWAYS.' 'THE CITY SHALL NOT BE LIABLE FOR ANY ERRORS AND/OR OMISSIONS ON THESE PLANS. ITEMS NOT MEETING CITY STANDARDS SHALL BE REPAIRED/REPLACED BY THE DEVELOPER/CONTRACTOR AND AT NO COST TO THE CITY.' If you have any questions, I can be reached at 791-4259 x76730 or Jose.Ortiz@tucsonaz.gov |
01/10/2008 | SMONTIE1 | UTILITY CLEARANCES | COT WATER NEW DEVELOPMENT | Denied | PLEASE SUBMIT UTILITY CLEARANCE LETTERS |
01/10/2008 | LANCE PETERSON | DOT STREET MAINTENANCE | REVIEW | Denied | We have reviewed this plan and have the following comments: 1. Sheet 1 - Note 25 - This note calls for the contractor to contact me for instructions. I have no idea what instructions that I would need to pass on to the contractor? 2. Who will be responcible for the maintenance of the D.G. path and the new landscaping? |
01/10/2008 | SMONTIE1 | UTILITY CLEARANCES | PC WASTEWATER MGMT | Denied | PLEASE SUBMIT UTILITY CLEARANCE LETTERS |
01/10/2008 | Blanca Espino | DOT ENGINEERING | REVIEW | Denied | PIA Plan 1. Please include a detail letter of explanation with the next submittal indicating where and how revisions were made. Single word responses are unacceptable. Include plans/redlines from previous plan submittal. 2. In title block, add assigned I-Plan Number, I-2007-054 to all sheets. 3. Indicate assigned DSD activity number T07PI00045 above title block. See redlines. 4. Indicate the following Paving Notes: q Pavement Section Design documentation, are in accordance to the approved Geotechnical Report, Report Name and Firm Name, Project Number. q The Engineer of Record shall submit for review of all changes to these plans and must be cleared and approved by the City of Tucson City Engineer's Permits and Codes Section, prior to construction. Additionally, the Engineer of Record shall certify all changes meeting all applicable standards, codes, and ordinances. q The PIA Inspector shall verify that the "Saw-cut" line is located within competent pavement. Adjustments to the plan shall be documented and As-built; a one foot minimum shall be provided. 5. All Easements, dedications, right-of-way should be depicted in plan view and labeled with recordation information (docket/page or plat book/page). See redlines for corrections. 6. Change the Cover sheet and Title block headings as per Sheet 1. Reflect the changes on Sheet 2. 7. Sheet 1, cover frame shall be shifted up at least .5 inches. 8. Sheet 1, Detail 1; Must coincide with drainage report. Indicate a dimensioned detail for the headwalls area. 9. Sheet 2, Key Note #6; Indicate if the curb return is to be concrete header all the way through the entrance up to the property line. 10. Indicate a profile of the 8-foot Multi-Use Pathway. Indicate Beginning, Ending and or various Points: Stationing, Offset from street centerline, and Elevation in Profile view. If alignment is identical to the 12-foot concrete pathway, indicate Stationing, Offset & Elevation every fifty feet in the Plan view. 11. Indicate Beginning, Ending and or various Points; Stationing, Offset from street centerline, and Elevation in Plan view for the 12-foot concrete pathway. 12. Indicate Beginning, Ending and or various Points; Stationing, Offset from street centerline, and Elevation in Plan view for the Saw-cut area. 13. Indicate Beginning & Ending; Stationing, Offset from street centerline, and Elevation in Plan & Profile views for the concrete headers. 14. Indicate Beginning & Ending; Stationing, Offset from street centerline in Plan view for the Barricade railing. 15. Plan Symbols and Abbreviations will be accepted only as per the PC/COT Standard Details for Public Improvement 2003 Edition. Use different line weights and line types to indicate Proposed or Existing structures. Existing structures must be shown with light color dashed lines. 16. Indicate the Street Centerline and Section line. Indicate symbol in Legend on cover sheet. 17. Pipe bedding shall conform to PC/COT Standard Detail 108. 18. Existing pavement thickness and surface treatment shall be matched. 19. See redlines for additional corrections. Once changes, modifications, and or corrections are made to the PIA plan resubmitted and reviewed, further comment may result. If you have any questions, I can be reached at 837-6634 or Blanca.Espino@tucsonaz.gov |
01/10/2008 | SMONTIE1 | UTILITY CLEARANCES | QUEST COMMUNICATION | Denied | PLEASE SUBMIT UTILITY CLEARANCE LETTERS |
01/10/2008 | SMONTIE1 | UTILITY CLEARANCES | TUCSON ELECTRIC POWER CO | Denied | PLEASE SUBMIT UTILITY CLEARANCE LETTERS |
01/10/2008 | SMONTIE1 | UTILITY CLEARANCES | COX COMMUNICATION | Denied | PLEASE SUBMIT UTILITY CLEARANCE LETTERS |
01/10/2008 | SMONTIE1 | UTILITY CLEARANCES | SOUTHWEST GAS CORP | Denied | PLEASE SUBMIT UTILITY CLEARANCE LETTERS |
01/10/2008 | SMONTIE1 | UTILITY CLEARANCES | EL PASO NATURAL GAS | Denied | PLEASE SUBMIT UTILITY CLEARANCE LETTERS |
01/10/2008 | SMONTIE1 | UTILITY CLEARANCES | KINDER MORGAN ENERGY | Denied | PLEASE SUBMIT UTILITY CLEARANCE LETTERS |
02/11/2008 | SMONTIE1 | PARK AND RECREATION | REVIEW | Approved | PARKS & Recreation Department Comments: Annexation- N/A (not applicable) Rezoning- N/A APPROVED- NO RESUBMITTAL REQUIRED. Reviewer: Joanne Hershenhorn Date: 2-8-08 |
02/11/2008 | SMONTIE1 | PIA COORDINATOR | CUSTOMER CALLED | Completed | |
02/11/2008 | SMONTIE1 | PIA COORDINATOR | OUT TO CUSTOMER | Completed |